By: Nathan Klosterman, Isaac Sprague, Jaime Gilbert, Logan Crain, Nick Gosseen, and Jerrod Miller. Belshaw Brothers Inc. Problem Statement. Silicon Boot that seals Cutter Head breaks after two weeks Lubricant and silicon boot pieces drop into donut batter
E N D
By: Nathan Klosterman, Isaac Sprague, Jaime Gilbert, Logan Crain, Nick Gosseen, and Jerrod Miller Belshaw Brothers Inc.
Problem Statement • Silicon Boot that seals Cutter Head breaks after two weeks • Lubricant and silicon boot pieces drop into donut batter • Takes over two hours to replace boot with a new one
Key Needs • Eliminate lubricant leaking into the donut batter • Design a boot that lasts longer • Keep same mounting points • Keep same plunger motion • Shorter boot replacement time
Concepts • Boot redesign – longer lasting
Concepts Trip Arm Redesign • Detachable • Machined Down
Concepts • Cam Bearing Material Change • Slide Plate Redesign
Final Design • FE analysis of boot Design • New design has 25% less stress First Choice Second Choice
Boot Redesign – Comparative Stress Analysis Final Design 1st Choice – 100% 2nd Choice – 61% Original – 100%
Final Design • Analysis of Detachable Trip Arm • New design is sufficiently strong • 31% of Yield Strength
Final Design • Tested of Machined Trip Arms • Removed oil leak path • Small amount of oil sticks to Drip Plate • Use in conjunction with new Drip Plate design
Final Design • Slotted Drip Plates • No real advantage • Use final design with machined Trip Arms • Removes remaining oil path
Final Design • Tested Oil-impregnated bronze bearing • Max PV value-50,000 • Calculated PV value-812 • Test results • Steel Bearing ~ • Bronze Bearing ~
Benchmarking • Eliminate lubricant leaking into the donut batter • Machined Trip Arms • Drip Plate Redesign • New Sleeve Bearing • Design a boot that lasts longer • New Design has 25% less stress • Keep same mounting points • Unchanged • Keep same plunger motion • Unchanged • Shorter boot replacement time • Detachable Trip Arms
Acknowledgements • Belshaw Brothers Inc. • Michael Wierman – Project Sponsor • Laura Nash – Engineer • MME Industrial Design Clinic • Dr. Charles Pezeshki • Dr. Kip Findley • Dr. Mesarovic • Harish Radhakrishnan