1 / 4

LAr at Point 1 : Power supplies

LAr at Point 1 : Power supplies. LVPS supplies electronics to a Front End crate 2*16 in Barrel, 2*13 in Endcaps LVPS takes 280V (from USA15) and makes +-4, 6, +-7, 11V up to 180A (total ~3kW) Modular : N module contributing to current. N+1 modules available for each voltage (27 modules/PS)

karena
Download Presentation

LAr at Point 1 : Power supplies

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LAr at Point 1 : Power supplies • LVPS supplies electronics to a Front End crate • 2*16 in Barrel, 2*13 in Endcaps • LVPS takes 280V (from USA15) and makes +-4, 6, +-7, 11V up to 180A (total ~3kW) • Modular : N module contributing to current. N+1 modules available for each voltage (27 modules/PS) • Radiation tolerant, Redundant, very tightly packed • Long story of failing manufacturing going back to year 2003 • Recurring problems lead to frequent exchanges during installation phase in pit • 2006: Task force (ATLAS, BNL, expert consultants) identified problems • Design issues • Fabrication issues • Proposed a complete reworking of the parts • 2007 Refurbishment: components, connectors, screws…. (~50 modifications/module) • During operation 2008 all LVPS worked OK but • 2 in redundant mode • 2 identified a “new” failure possibility not addressed in 2007 Campaign 2008-09 : new retrofitting campaign (all 58 LVPS from point 1 to US and back)

  2. LAr at Point 1 : LVPS To come • One [known] unsolved issue (Capacitor damage “C26”) we could not find a better replacement • 58 LVPS in operation since April 09, no failures, no redundant mode • If one “C26” fails, that voltage goes into redundant mode. LVPS can operate OK. • Would need to have a new failure in one of the other ~4 modules of that voltage. • Conclusion: we have fixed all we could • LVPS in good shape, redundancy should work • Medium term: producing a new set of LVPS • 2 Vendors contacted • Phase 1: Single voltages modules of correct size, done OK • Currently making full prototypes (delivery ~September09) • Choice of vendor End 2009 • Production 1st half 2010 • Prove reliability of series off detector (?) • Installation when access permits

  3. LAr at Point 1 : OTx • OTx is the optical transmitter sending off the serialized data of one FEB to the ROD. • Mezzanine : little circuit + Laser emitter (VCSEL) coupling onto fiber with ST connector • 1 OTx / FEB (Tiles has 2!) • Reliable devices were difficult to obtain in 2005 at the time of FEB production • After QC and other improvements devices were acceptable • Extra steps of QC … • Problems seemed solved • No failures during ~1.5 years

  4. LAr at Point 1 : OTx • In 2008 operation ~8 devices failed • Abruptly • Not correlated to anything obvious (B, power on, humidity) • All replaced during shutdown • In 2009 they keep failing, ~1/week (out of the 1600) • By now (since detector closed in May) 5 dead • Happen anywhere (now 4 Front, 1 Middle) • Always : VCSEL is the element failing • Task force analyzing the causes and preparing actions • No root cause yet • Also failed efforts to estimate the size of problem • ESD damage at the time of fabrication is main suspect • Expect some results from FA experts starting now • Preparing backup device • Other VCSEL, similar circuit, similar mezzanine, produced under best conditions • Double VCSEL, but would need two fibers. Difficult installation (eg. in EC chains) • Replacing all OTx’s is a BIG operation • Unclear when it could take place • Effects can be mitigated with L1 Trigger readout

More Related