1 / 19

Chapter 9 Cost Planning and Performance

Chapter 9 Cost Planning and Performance. Learning Objectives. Items to consider when estimating cost Preparing a baseline budget Cumulating actual costs Determining the earned value of work performed Analyzing cost performance Forecasting project cost at completion

karsen
Download Presentation

Chapter 9 Cost Planning and Performance

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Chapter 9Cost Planning and Performance

  2. Learning Objectives • Items to consider when estimating cost • Preparing a baseline budget • Cumulating actual costs • Determining the earned value of work performed • Analyzing cost performance • Forecasting project cost at completion • Controlling project costs • Managing cash flow 2 2 2

  3. Real World Example • Vignette: Hygeia Travel Health – a Toronto-based health insurance company • Developed a structured process to help it forecast cost and benefits that is used for every project. • A project evaluation committee of six members is split into two groups. • All costs are evaluated by each group and then the results are compared. • Each project is then approved, rejected, or tabled for future consideration. • Hygeia stresses the importance of evaluating all project costs before a project begins. 3 3 3

  4. Real World Example • Vignette: RWD Technologies – A company that has always been a strong believer in project management methodologies • Shortly after the company was formed an internal project management training program was created. • RWD Technologies has tackled hundreds of successful projects such as lean manufacturing at Daimler-Chrysler, Ford and General Motors; ERP implementations for more than 100 clients; and various web-based applications for Whirlpool and Proctor & Gamble.

  5. Project Cost Estimates • Cost planning starts with the proposal. • The cost section may include: • Labor • Materials • Subcontractors and consultants (if used) • Equipment and facilities rental • Travel 4

  6. Project Budgeting: Two Steps • First, the project cost estimate is allocated to the various work packages in the project work breakdown structure. • Second, the budget for each work package is distributed over the duration of the work package. 5

  7. Allocating the Total Budgeted Cost • Allocating total project costs for the various elements to the appropriate work packages will establish a total budgeted cost (TBC) for each work package. • There are two approaches to establishing the TBC for each work package: top-down and bottom-up. • When all budgets are summed, they cannot exceed the TBC. 6

  8. Developing the Cumulative Budgeted Cost • The second step is to distribute each TBC over the duration of its work package. • A cost is determined for each period. • The cumulative budgeted cost (CBC) is the amount that was budgeted to accomplish the work that was scheduled to be performed up to that point in time. • One uses the CBC as the standard against which actual cost is compared. 7

  9. Determining Actual Cost • Track actual cost by establishing a system to collect data on funds actually expended. • Periodically assign a portion of the total committed cost to actual cost. • Total actual and committed cost by work package for comparison to the CBC. • Cumulative actual cost (CAC) should be calculated. 8

  10. Determining the Value of Work Performed • Earned value is the value of the work actually performed. • Determine earned value by collecting data on the percent complete for each work package. • Convert this percentage to a dollar amount by multiplying the TBC of the work package by the percent complete. 9

  11. Cost Performance Analysis Four Measures • TBC (total budgeted cost) • CBC (cumulative budgeted cost) • CAC (cumulative actual cost) • CEV (cumulative earned value) 10

  12. Cost Performance Index (CPI) • A measure of the cost efficiency with which the project is being performed. • Cost performance index = F(Cumulative earned value,Cumulative actual cost) • CPI = F(CEV,CAC) 11 1

  13. Cost Variance (CV) • The difference between the cumulative earned value of the work performed and the cumulative actual cost. • Cost variance =Cumulative earned value – Cumulative actual cost • CV = CEV – CAC 12

  14. Cost Forcasting Three Methods • Three methods for determing forecasted cost at completion (FCAC): • FCAC = F(Total budgeted cost,Cost performance index) • FCAC = Cumulative actual cost + (Total budgeted cost – Cumulative earned value) • FCAC = CAC + Re-estimate of remaining work to be performed 13

  15. Cost Control • The key is to analyze cost performance on a regular and timely basis. • Identify cost variances and inefficiencies early. 14

  16. Cost Control (Cont.) • Involves the following: • Analyzing cost performance to determine which work packages may require corrective action. • Deciding what corrective action should be taken • Revising the project plan. 15

  17. Ways to Reduce Costs of Activities • Substitute less expensive materials. • Assign a person with greater expertise to perform or help with the activity. • Reduce the scope or requirements. • Increase productivity through improved methods or technology. 16

  18. Managing Cash Flow • Make sure that sufficient payments are received from the customer in time for you to cover the costs of performing the project. • The key to managing cash flow is to ensure that cash comes in faster than it goes out. 17

  19. Project Management Software • All costs associated resources can be stored. The software calculates the budget for each work package and for the entire project. • The software allows the user to define different rate structures for each resource and when charges for those resources will be accrued. • Cost tables and graphs are available to help analyze cost performance. 18

More Related