WMS UPDATE

WMS UPDATE. Disputes There have been approximately 6,686 disputes filed so far in 2003 categorized as follows: Balancing Energy – 3,628 OOM – 1,599 Ancillary Services – 910 RMR – 415 Fees – 62 Black Start – 53 Congestion Management Energy – 16 Other – 2. WMS UPDATE.

Download Presentation

WMS UPDATE

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. WMS UPDATE Disputes There have been approximately 6,686 disputes filed so far in 2003 categorized as follows: • Balancing Energy – 3,628 • OOM – 1,599 • Ancillary Services – 910 • RMR – 415 • Fees – 62 • Black Start – 53 • Congestion Management Energy – 16 • Other – 2

  2. WMS UPDATE Of the above disputes, • 4,103 (61%) have been denied, 1,063 (16%) have been granted with exceptions, 471 (7%) have been granted, and 1,049 (15%) are open. Twenty-three ADRs have been filed so far in 2003.

  3. WMS UPDATE OOME Instructed Deviation Workaround • QSE’s that get unit specific OOME instructions can request a Verbal Dispatch Exception (VDE). • The VDE is a note to ERCOT Settlements that the OOME instruction should be treated as an instructed deviation for settlement purposes (URC calculation).

  4. WMS UPDATE • A VDE can only be requested due to a unit specific OOME instruction and must be requested when the instruction is received. • The ERCOT operator approves the request and passes the information to Settlements. • The amount of the VDE is the amount that the zidup or ziddn shall be adjusted in the Settlement System. A VDE is not the same as a Zonal OOM Instruction.

  5. WMS UPDATE • Settlements shall calculate the amount of the VDE based on the RP and IOL passed to Settlements from the MOS. • The workaround cannot be effective until operating day January 15, 2004 or later

  6. WMS UPDATE PRR 404 Credit Issues • The ERCOT Settlements group has devised a method to identify the required information one day after the Operating Day. • Additional collateral will be required if MWhs required exceed the QSE’s schedule; however, the amount of that collateral required (as a percentage) has not yet been determined. • The same issue is unresolved for the incremental collateral calculation although some of the required information for this calculation is not available until seven days after the Operating Day. • The Credit Group continues to work on the outstanding issues and will provide it’s decision to WMS.

  7. WMS UPDATE Zone Addition System Impact • If more than five zones are selected, a re-architecture effort to improve the systems would be required. • Initially ERCOT will not change any timing on deployment, but if processing delay times become apparent, the calculation start times would be adjusted. • Similar effects are noted in both EMMS and Lodestar relative to processing times.