An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Algorithm Growth Risk R&O Splinter June 8, 2011

  2. Background • IDPS-14 Algorithm Growth risk was reviewed at 27 May CGS ROMB • Recommendation was to brief R&O Splinter on algorithm size and delivery schedule currently incorporated into JPSS baseline • ROMB was concerned that the customer was not aware of the specifics of the planned algorithm work • ROMB recommendation is the risk of algorithm growth should be transferred to NASA to manage

  3. Algorithm Baseline • Algorithm drops • Drop sizes as listed in the JPSS proposal • Schedule as planned during DRW 11 • Note that 5,000 DSLOC is in process of being repurposed for Cal/Val support as briefed in IDPS Splinter to DPA/DPE Re-purpose FY11-12 drops to Cal/Val algorithm support in FY12-13

  4. Summary • Raytheon has incorporated specific algorithm sizes and delivery dates into their baseline plan • Raytheon has opened a risk in the case that algorithm deliveries from NASA are larger than planned • Raytheon recommends that the risk should be transferred to NASA to manage