An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FLO-2D Model Development Below Caballo Damto Ft. Quitman Prepared by: U.S. Army Corps of Engineers Albuquerque District and Mussetter Engineering, Inc.

  2. Canalization Reach - Caballo to American Dam • Flo-2D model development complete • Tributary studies – gaging analysis

  3. Basic (Big Flood) Results • Area of Inundation • Flood hydrographs every 250 ft of channel • Flood wave attenuation • Levee deficiency and overtopping

  4. Area of Inundation Maps

  5. Flood Hydrographs 2004 Calibration Results Haydon Gage

  6. 2004 Calibration Results Leasburg Gage

  7. 2004 Calibration Results Mesilla Gage

  8. 2004 Calibration Results Anthony Gage

  9. Floodwave Attenuation

  10. Levee Freeboard Deficiency

  11. Levee Deficiency Code was written to track the maximum loss of levee freeboard as requested by IBWC. This can be reviewed as an option in MAXPLOT (also in Mapper by swapping files).

  12. Potential future benefits • Flood risk and hazard assessment • Flood mitigation – raise levees • Local flood details – levee elevations, wasteways, urban flooding • Revise flood hydrology • River operations • River maintenance response • River restoration response

  13. Resolved Issues • Which hydrology and dam release to use • Diversion dam operation during flooding • How do wasteways function during flooding • Levee deficiency • Road embankments – detail for local flooding • Sediment loading

  14. Return Period Flood Modeling The various return period tributary flood inflows using the revised hydrology were simulated with the typical irrigation release of 2,350 cfs. Return period floods were: 2-yr, 5-yr, 10-yr, 25-yr, 50-yr, 100-yr

  15. Sediment Yield • To determine an appropriate sediment supply to the RGCP, it was recommended that the sediment load analysis be refined • Update the NRCS reservoir survey data

  16. Sediment Yield Equation • The equation for total sediment load QT was of the form: • QT = A1 + A2 Ab + A3 Log (Ab) • where: A1, A2, and A3 are regression coefficients and Ab is the basin area.

  17. Sediment Load Adjustment Sediment yield per unit area was plotted as f(basin area). A decreasing power function could be applied to adjust the sediment yield equation as function of the basin area. The derived adjustment equation was: Fa = 5.69 * Ab(-0.3739) where: Fa is the adjustment factor

  18. Tributary Inflow Gage analysis

  19. Rectification Reach – American Dam to Ft. Quitman BI-NATIONAL PROJECT KICK-OFF MEETING October 18, 2005 - El Paso, TX

  20. Overall Goal This Project Will Result In A Functional, Calibrated, Two-Dimensional Flood Routing Model For The Rio Grande Between American Dam and Fort Quitman, Texas • Plus Ancillary Products!

  21. Rectification Reach – Water Operations • Limited to flood control operations at Caballo Dam and Reservoir • Input Hydrographs at American Dam (Results from Canalization Reach FLO-2D) + Tributary Contributions

  22. PROJECT TIMELINE • The entire project will take 1 year to complete • Hydrology – 60 days • Tributary Sediment Analysis – 90 days • Hydrographic Data Collection (Cross Sections) – 120 days • FLO-2D Model Development – 90 days • FLO-2D Model Calibration – 30 days • Final Report – On-Going throughout Study

  23. HYDROLOGY • Develop Flood Hydrographs at Significant Tributary Confluences with Rio Grande

  24. Reach Based Effort • Tributary Models • American side • Mexican side

  25. The End October 18, 2005