An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Management ___________________________________________________________________________ Operations Research  Jan Fábry

  2. Project Management • Project Activity 5 Activity 2 Activity 1 Activity 7 Activity 3 Activity 4 Activity 6 ___________________________________________________________________________ Operations Research  Jan Fábry

  3. Activity 5 Activity 2 Activity 1 Activity 7 Activity 3 Activity 4 Activity 6 Project Management NETWORK – graphical representation of the project Activity  Node ___________________________________________________________________________ Operations Research  Jan Fábry

  4. ACT 4 5 2 ACT 9 ACT 1 ACT 5 ACT 6 ACT 10 6 ACT 2 1 8 3 ACT 7 ACT 3 ACT 11 7 4 ACT 8 6 2 4 1 5 6 2 3 Project Management NETWORK – graphical representation of the project Activity  Arc ___________________________________________________________________________ Operations Research  Jan Fábry

  5. 1 3 2 Start pointof A Finish pointof A Start pointof B Finish pointof B Project Management • Event Activity ADesign a car Activity BMake a prototype ___________________________________________________________________________ Operations Research  Jan Fábry

  6. Activity ADesign a car Activity BMake a prototype 1 3 2 Project Management Activity A immediately PRECEDES activity B Activity B immediately SUCCEEDS activity A ___________________________________________________________________________ Operations Research  Jan Fábry

  7. Activity BMake a prototype 3 Activity ADesign a car 1 2 Activity CComputer presentation 4 Project Management Activity A is the predecessor of Activity B and C ___________________________________________________________________________ Operations Research  Jan Fábry

  8. Activity EPrototype test Activity BMake a prototype 5 3 Activity ADesign a car Dummyactivity 1 2 Activity DPrototype presentation Activity CComputer presentation 4 Project Management Activity E (Prototype test) follows Activity B Activity D(Prototype presentation) follows Activity BandC ___________________________________________________________________________ Operations Research  Jan Fábry

  9. Project Management Activity Requirements - time - money (cost) - material - machines - people ___________________________________________________________________________ Operations Research  Jan Fábry

  10. Planning Network Start and finish times for each activity Finish time of project • Scheduling Periodic progress reports • Controlling Project Management Phases of Project Management ___________________________________________________________________________ Operations Research  Jan Fábry

  11. Critical Path Method (CPM) Program Evaluation Review Technique (PERT) Project Management Methods Deterministic time Probabilistic time ___________________________________________________________________________ Operations Research  Jan Fábry

  12. Project Management CPM ___________________________________________________________________________ Operations Research  Jan Fábry

  13. Project Management CPM • Finish time of the project • Start and finish times of each activity • A critical path consisting of critical activities • Non-critical activities and their possible delay ___________________________________________________________________________ Operations Research  Jan Fábry

  14. Project Management CPM Example - Music DM, Inc. • Christmas compilation of Czech carols • 11 activities: 1) Songs Selection 2) Mastering 3) Promotion Material Elaborating ___________________________________________________________________________ Operations Research  Jan Fábry

  15. Project Management CPM Example - Music DM, Inc. • 11 activities: 4) Customers Analysis 5) Promotion Material Production 6) Make CD Copies 7) Customers Selection ___________________________________________________________________________ Operations Research  Jan Fábry

  16. Project Management CPM Example - Music DM, Inc. • 11 activities: 8) Data to Printing House 9) Promotion Material to Printing House 10) Laser Print 11) Mailing ___________________________________________________________________________ Operations Research  Jan Fábry

  17. Project Management CPM Example - Music DM, Inc. ___________________________________________________________________________ Operations Research  Jan Fábry

  18. Project Management CPM Example - Music DM, Inc. • All the envelopes have to be delivered until December 12 • Objective: set the starting date of the project ___________________________________________________________________________ Operations Research  Jan Fábry

  19. Project Management CPM Example - Music DM, Inc. Solution - CPM 1) Construct the network 2) Event analysis - forward pass - backward pass 3) Activity analysis - critical activities - noncritical activities ___________________________________________________________________________ Operations Research  Jan Fábry

  20. Project Management CPM Example - Music DM, Inc. 1) Construct the network One start node & one end node Each activity  one arc Two nodes are connected maximally by one arc ___________________________________________________________________________ Operations Research  Jan Fábry

  21. i 2 3 j 3 2 Project Management CPM Example - Music DM, Inc. 1) Construct the network i < j ___________________________________________________________________________ Operations Research  Jan Fábry

  22. Project Management CPM Example - Music DM, Inc. ___________________________________________________________________________ Operations Research  Jan Fábry

  23. Project Management CPM Example - Music DM, Inc. ___________________________________________________________________________ Operations Research  Jan Fábry

  24. H K B D2 J A D G I D1 C F E 6 4 3 9 5 7 8 10 2 1 Project Management CPM Example - Music DM, Inc. ___________________________________________________________________________ Operations Research  Jan Fábry

  25. 12 8 8 9 0 15 7 3 3 0 6 5 4 6 4 3 9 5 7 8 10 2 1 Project Management CPM Example - Music DM, Inc. ___________________________________________________________________________ Operations Research  Jan Fábry

  26. j ETj Project Management CPM Example - Music DM, Inc. 2) Event analysis - forward pass The earliest event time for a nodeis the earliest time at which all the preceding activities have been completed. ___________________________________________________________________________ Operations Research  Jan Fábry

  27. Project Management CPM Example - Music DM, Inc. 2) Event analysis - forward pass Ascending order: ET1ET2ET3 … ETn The earliest event time for completing a projectis the earliest time of the last event. T = ETn ___________________________________________________________________________ Operations Research  Jan Fábry

  28. i LTi Project Management CPM Example - Music DM, Inc. 2) Event analysis - backward pass The latest event time for a nodeis the latest time at which the event can occur without delaying the determined completion time of the project. ___________________________________________________________________________ Operations Research  Jan Fábry

  29. Project Management CPM Example - Music DM, Inc. 2) Event analysis - backward pass Descending order: LT1LT2LT3 …  LTn The latest event time for completing a project can be set in the planning process or can be considered as the earliest event time for completing a project. LTn = T = ETn or LTn = TPL > T ___________________________________________________________________________ Operations Research  Jan Fábry

  30. i j tij ETi LTi ETj LTj Project Management CPM Example - Music DM, Inc. 3) Activity analysis Total float: ___________________________________________________________________________ Operations Research  Jan Fábry

  31. Project Management CPM Example - Music DM, Inc. 3) Activity analysis Critical activity: TFij = 0 if LTn = T = ETn TFij = TPL - T if LTn = TPL > T Noncritical activity: TFij > 0 if LTn = T = ETn TFij > TPL - T if LTn = TPL > T ___________________________________________________________________________ Operations Research  Jan Fábry

  32. H K B D2 J A D G I D1 C F E 8 4 3 7 6 9 5 10 2 1 Project Management CPM Example - Music DM, Inc. 3) Activity analysis Critical path: ___________________________________________________________________________ Operations Research  Jan Fábry

  33. Project Management CPM Example - Music DM, Inc. 3) Activity analysis Noncritical activity 1) Start of the activity can be postponed 2) Duration of the activity can be extended 3) Combination of 1 and 2 ___________________________________________________________________________ Operations Research  Jan Fábry