1 / 82

BA 333 Operations Management

BA 333 Operations Management. Project Management PERT/CPM Spring, 1998. Lecture Outline. Project Management Introduction Definition & Background Components event activity critical path PERT/CPM. Introduction to Project Management. Definition

keala
Download Presentation

BA 333 Operations Management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BA 333Operations Management Project Management PERT/CPM Spring, 1998

  2. Lecture Outline • Project Management Introduction • Definition & Background • Components • event • activity • critical path • PERT/CPM

  3. Introduction to Project Management • Definition • to plan, implement, and control the management of large, one time projects • Used in Construction, Shipbuilding, Weapons Systems Development, etc. • Applies to uncertain technology projects • Applies to variable cost resource allocation • History of PERT/CPM - Navy/Booze Allen Hamilton Consultants

  4. Introduction to Project Scheduling

  5. Components of Project Control Systems • Predecessor was Gantt Charts • Horizontal Bar Charts - Time Lines • Tasks • Milestones • Flow Charts - Relationships Among All Tasks • Activities (tasks that take time and resources) • sequential vs. concurrent • Events (an accomplishment occurring at a specific point in time)

  6. Project Characteristics • Single unit • Many related activities • Difficult production planning & inventory control • General purpose equipment • High labor skills

  7. Examples of Projects

  8. Examples of Projects • Building construction  © 1995 Corel Corp.

  9. Examples of Projects • Building construction • New product introduction New! Improved! 19 · Nude Sandalfoot Medium to Tall (B) No nonsense Sheer to waist pantyhose © 1995 Corel Corp.

  10. Examples of Projects • Building construction • New product introduction • Training seminar © 1995 Corel Corp.

  11. Examples of Projects • Building construction • New product introduction • Training seminar • Research project © 1995 Corel Corp.

  12. Project Management Activities

  13. Project Management Activities

  14. Project Management Activities • Planning • Objectives • Resources • Work break-down sched. • Organization

  15. Project Management Activities • Planning • Objectives • Resources • Work break-down sched. • Organization • Scheduling • Project activities • Start & end times • Network

  16. Project Management Activities • Planning • Objectives • Resources • Work break-down sched. • Organization • Scheduling • Project activities • Start & end times • Network • Controlling • Monitor, compare, revise, action

  17. Project Planning

  18. Project Planning • Establishing objectives • Defining project • Creating work breakdown structure • Determining resources • Forming organization © 1995 Corel Corp.

  19. Project Organization • Often temporary structure • Uses specialists from entire company • Headed by project manager • Coordinates activities • Monitors schedule & costs • Permanent structure called ‘matrix organization’ Eng. Eng. Mkt. Acct. Mgr. © 1995 Corel Corp.

  20. Project Scheduling

  21. Project Scheduling • Sequencing activities • Identifying precedence relationships • Determining activity times & costs • Estimating material & worker requirements • Determining critical activities PERT J Test J M A Build M F Month Design J Activity © 1995 Corel Corp.

  22. Project Scheduling Techniques • Gantt chart • Critical Path Method (CPM) • Program Evaluation & Review Technique (PERT) © 1984-1994 T/Maker Co.

  23. Gantt Chart

  24. Gantt Chart

  25. PERT & CPM • Network techniques • Developed in 1950’s • CPM by DuPont for chemical plants • PERT by U.S. Navy for Polaris missile • Consider precedence relationships & interdependencies • Each uses a different estimate of activity times

  26. Questions Answered by PERT & CPM • Completion date? • On schedule? Within budget? • Probability of completing by ...? • Critical activities? • Enough resources available? • How can the project be finished early at the least cost?

  27. PERT & CPM Steps • Identify activities • Determine sequence • Create network • Determine activity times • Find critical path • Earliest & latest start times • Earliest & latest finish times • Slack

  28. Constructing Networks

  29. Graphical Representation of Events and Activities • Flow Charting - Uses Nodes and Arrows • Arrows • An arrow leads from tail to head directionally • Nodes • A node is represented by a circle Arrow Node

  30. 1 2 3 Activity On Node • Task is Represented by Node as the Completion of an Activity • Arrows Represent the Sequential Linkages Between Activities • For Example, Node 1 is Begin, Node 2 is Complete Task 1, Node 3 is Complete Task 2

  31. 1 2 Activity On Arrow • Task is Represented by an Arrow Bounded on Either End by a Node (Event) • Each Event is Identified by a Number • The Activity is Designated by the Leading Event Number and the Following Event Number - i.e. Activity 1 - 2

  32. 1 2 3 2 1 4 3 Designating Task Relationships • Sequential vs. Concurrent Activities Sequential Task Relationship Concurrent Task Relationships

  33. Designating “DUMMY” Activities • Represented by Dashed Arrows • Show Sequential Relationships Among Tasks, but Take No time or Resources 2 1 4 Dummy Activity 2-3 indicates that both Activities 1-2 and 2-3 must be Completed before beginning Activity 3-4 3

  34. Network Terms

  35. Network Terms Project: Obtain a college degree (B.S.)

  36. Network Terms Project: Obtain a college degree (B.S.) Register 1

  37. Network Terms Project: Obtain a college degree (B.S.) Register 1 Event (Node)

  38. Network Terms Project: Obtain a college degree (B.S.) Register Attend class, study etc. 1 4 Years Event (Node)

  39. Network Terms Project: Obtain a college degree (B.S.) Register Attend class, study etc. 1 4 Years Activity (Arrow) Event (Node)

  40. Network Terms Project: Obtain a college degree (B.S.) Receive diploma Register Attend class, study etc. 1 2 4 Years Activity (Arrow) Event (Node) Event (Node)

  41. Activity Relationships

  42. Activity Relationships 1

  43. Activity Relationships 2 A 1 3 B A & B can occur concurrently

  44. Activity Relationships A must be done before C & D can begin 2 D A C 1 4 3 B

  45. Activity Relationships 2 D A C 1 4 3 B E B & C must be done before E can begin

  46. Dummy Activities • Activities are defined often by beginning & ending events • Example: Activity 2-3 • Every activity must have unique pair of beginning & ending events • Computer programs get confused • Dummy activities maintain precedence • Consume no time or resources

  47. Dummy Activities Example

  48. Dummy Activities Example 2-3 Incorrect 1-2 3-4 1 2 3 4 2-3

  49. Dummy Activities Example 2-3 Incorrect 1-2 3-4 1 2 3 4 2-3 Different activities; same designation

  50. Dummy Activities Example 2-3 Incorrect 1-2 3-4 1 2 3 4 2-3 Correct 1-2 2-4 4-5 4 1 2 5 3 2-3 3-4: Dummy activity

More Related