An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Board of County Commissioners Public Hearings June 3, 2014

  2. Fishback Property Planned Development Case:CDR-13-12-298 Project:Fishback Property Planned Development / The Vineyards Phases 1 & 2 Preliminary Subdivision Plan Applicant:Adam Smith, VHB, Inc. District: 1 Request:Substantial Change to existing PD to adjust the recreation area to include one (1) pool and one (1) cabana in lieu of two (2) pools and two (2) cabanas

  3. Fishback Property Planned Development

  4. Fishback Property Planned Development

  5. Fishback Property Planned Development Action Requested Make a finding of consistency with the Comprehensive Plan and approve the substantial change to the Fishback Property PD / The Vineyards Phases 1 & 2 Preliminary Subdivision Plan, subject to the conditions listed in the staff report.

  6. Moss Park Planned Development Case:PSP-13-08-204 Project:Moss Park Planned Development / Western Portion of Parcel N Preliminary Subdivision Plan Applicant:Lance Bennett, Poulos and Bennett, LLC District: 4 Acreage: 142.92 acres Request: Construction of 309 single-family detached residential dwelling units

  7. Moss Park Planned Development

  8. Moss Park Planned Development

  9. Moss Park Planned Development

  10. Moss Park Planned Development Moss Park Revisions: Revised Unit Count: 309 Revised COA #8:  The applicant must apply for a capacity encumbrance letter prior to construction plan submittal and must apply for and obtain a capacity reservation certificate prior to platting.  Nothing in this condition, and nothing in the decision to approve this preliminary subdivision plan, shall be construed as a guarantee that the applicant will be able to satisfy the requirements for obtaining a capacity encumbrance letter or a capacity reservation certificate. Revised COA #13:  Developer shall provide pedestrian connectivity to the Innovation Way South sidewalk from Park & Rec Tracts P3 and P4 at the time Tract FD02 is developed.

  11. Moss Park Planned Development Moss Park Revisions: Proposed New COA #18: Within 150 days of approval of this PSP and prior to the platting and recordation of the plat of Phase 2 of the Moss Park PD, Developer shall cause the modification of the Conservation Easement granted to the South Florida Water Management District recorded in Orange County Official Records Book 08562, Pages 3365-3384 to allow for passive recreation within the conservation easement area. Within 30 days of the recording of the Amended Conservation Easement and prior to any construction, Developer shall convey to the County by Special Warranty Deed the northerly 4 acres of that area described as Wetland 20 in the above-described Conservation Easement and is contiguous to county-owned property, in accordance with County requirements, including but not limited to an acceptable signed and sealed legal description and sketch, Title Insurance Commitment evidencing the property is free and clear of all liens and encumbrances except the Amended Conservation Easement. The Developer shall be solely responsible for all costs associated with the conveyance.

  12. Moss Park Planned Development Action Requested Make a finding of consistency with the Comprehensive Plan and approve the Moss Park Planned Development / Western Portion of Parcel N Preliminary Subdivision Plan, subject to the conditions listed in the staff report.

  13. Kerina Parkside Planned Development Case:PSP-13-05-116 Project:Kerina Parkside Planned Development / Parkside Tract 2 Preliminary Subdivision Plan Applicant:David Kelly, Donald W. McIntosh Associates, Inc. District: 1 Acreage: 36.3 acres Request: Construction of 112 single-family detached residential dwelling units

  14. Kerina Parkside Planned Development

  15. Kerina Parkside Planned Development

  16. Kerina Parkside Planned Development Kerina Parkside Revisions: Proposed New COA: A six (6) foot high PVC fence shall be provided along the rear of proposed lots 24 through 33.

  17. Kerina Parkside Planned Development Action Requested Make a finding of consistency with the Comprehensive Plan and approve the Kerina Parkside PD / Parkside Tract 2 Preliminary Subdivision Plan, subject to the conditions listed in the staff report.

  18. Board of County Commissioners Public Hearings June 3, 2014