1 / 46

Design Build in Federal Contracting Legal and Contractual Issues in a Military Design Build Projects

Design Build in Federal Contracting Legal and Contractual Issues in a Military Design Build Projects. The 2007 NC State University Military Design/Build Forum May 21, 2007 1:00 -1:45 p.m. Introduction. Joe Henner, Esq. Partner with Kilpatrick Stockton LLP Construction Lawyer for 19 years

keaton
Download Presentation

Design Build in Federal Contracting Legal and Contractual Issues in a Military Design Build Projects

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Design Build in Federal ContractingLegal and Contractual Issuesin a Military Design Build Projects The 2007 NC State University Military Design/Build Forum May 21, 2007 1:00 -1:45 p.m.

  2. Introduction • Joe Henner, Esq. • Partner with Kilpatrick Stockton LLP • Construction Lawyer for 19 years • Practiced Throughout United States • Ten Years of Pure Litigation with Design-Bid-Build Projects • Last Nine Years, Front End Delivery Systems and Day to Day Advice

  3. PERSPECTIVES: First Word • Owner-Public and Private • Architect • Program Manager/Construction Manager • Construction Manager at Risk/GC • Subcontractor • Attorney

  4. Session Goals • Understand Key Differences between Design Build and Design-Bid-Build • Understand History and Development of Design Build Laws • Discuss Practical Steps to Minimize Risks of Design Build

  5. Project Delivery: Definition • Project delivery systems define the structural framework for the Owner’s development and management of a construction project

  6. Design/Build Delivery Method • What is Design-Build? • Whenever there is a sole source responsible for both designing and constructing the project, the delivery system is design-build

  7. Design-Bid-Build

  8. Design/Build

  9. Design Build • Provides single point of accountability for delivery of complex projects • Aligns incentives with owner’s goals and increases likelihood of a successful project.

  10. Design Build • Design Liability is Reduced/Eliminated • History Show a Reduction of Liability Exposure • integration of design & construction promotes cooperation • partnering approach • Key is to understand project risks and how to address them

  11. Design Build Issues • Designing to budget • Role of contractor during design • Duties during construction administration • Financial considerations • Bonds • Contingencies • Bonus/penalty • E&O coverages

  12. Distinguish Design Build vs DBB • Lump Sum or GMP includes everything that is reasonably inferable for D/B • In Design-Bid-Build, the GC is only responsible for what is clearly shown on the plans and specifications • Generally, the Change Orders for non land issues are covered by the Contractor’s Contingency.

  13. Distinguish Design Build vs DBB • In Traditional Role, the Architect has its right arm around the Owner. • In D/B, the Architect is a subcontractor to the Design/Build Contractor. • The D/B Contractor is responsible for the quality and timeliness of the design • All coordination issues rest with the D/B Contractor

  14. History of Design/Build • During the 1900s, competitive bidding laws required what is now known as the Traditional Approach • Owner hired Designer based on qualifications and hired the low bid contractor.

  15. History of Design/Build • Historically, all major construction feats were performed by Master Builders who designed and built the structure. • 1940s Naval Facilities Engineering Command used D/B on housing projects • In 1962, NASA used D/B • In 1972, Brooks Act is passed

  16. History of Design/Build • Architects Filed Lawsuits Fighting Against Design/Build laws. • The Brooks Act requires all Federal agencies to select the most qualified designers and price is precluded from the qualifications.

  17. Current Laws for Design/Build • In 1992, ASCE approved a Policy Statement on Design/Build in the Federal Sector • In 1997, the AIA Board released a Position Statement re Public Sector D/B • In 2000, the DBIA published a Guide to the Federal Design/Build Marketplace

  18. History of Design Build • Military Construction Authorization Act of 1986 allowed D/B on a limited basis • Use of Design/Build in the Public Sector doubled from 1986 to 1992 • 1994 and 1996 new laws passed using “best Value” • Federal Acquisition Streamlining Act of 1994 • National Defense Authorization Act of 1996

  19. Current Design/Build Laws • These laws permit the use of a 2 step process. • All Federal executive agencies are permitted to use D/B if that method is appropriate for the Public Project. • The first phase is to evaluate “specialized experience and technical competence.” NO COST • The second phase is the bid with award to highest ranked proponent, including qualifications and price.

  20. Current D/B Laws • In 1997, the Federal Government created the rules for design build Projects. • The Federal Acquisition Regulations codified the required Design/Build Procedures • See 48 CFR Sections 36.102-36.104 and 36.300-36.303

  21. Current D/B Laws • In 1998, Congress passed the Transportation Equity Act for the 21st Century (TEA-21, Section 1307) • Endorsed D/B for its speed, economy and effficiency. • In 1999, the Airport Improvement Program permitted the use of D/B on 7 projects

  22. Alternative Delivery Methods • Most States Have Adopted StatutesPermitting Alternative Delivery Methods • The Standard State Statutes now allow CM at Risk, Design/Build and other delivery methods • Fifty State Construction Contracting • DBIA website; www.dbia.org • Trending toward utilization of all delivery methods

  23. Design/Build: Initial Considerations • Procurement Statutes • Licensing Laws • Insurance Coverage • Performance Bond Coverage • Subcontractors • Lines of Communication

  24. D/B’s Biggest Challenge • THE MAIN CHALLENGE/CHANGE FOR CONTRACTORS WITH D/B IS CONTROLLING DESIGN LIABILITY

  25. Design - BuildShades of Gray • Owner’s Technical Expertise • Owner’s Design Involvement • Limitations Imposed on Design • Superior Knowledge • Comparative Fault • Partial Design • Terms of Solicitation • Information Provided • Terms of the Contract

  26. Quasi Design/Build Projects • Owners, for example the Ga. DOT, have advertised Design/Build Projects with 90% complete designs. • “Bridging Documents” • Does a D/B Architect want to accept liability for another Architect’s work?

  27. Key Contract IssuesPerformance Guarantees • An Obligation That all Or Part of The Project Will Perform In A Certain Way • Strict Liability • Not Unique to Design-Build • Like Performance Specifications • Strong Influence On Design-Build Choice • Product Output, Energy Usage, Pollution Discharges • Enforceable If Clear & Unambiguous

  28. Key Contract IssuesImplied Warranty • Implied Warranty of Fitness For A Particular Purpose • Strict Liability

  29. Key Contract IssuesStandard of Care • Design Functions • Baseline For Evaluating Negligence • Only If No Guarantees/Warranties • Even If Unstated It Applies • Standard of Care May Be Raised • By Express Statement • By Special Expertise • Construed As Performance Guarantee?

  30. Key Contract IssuesFlow-Down Obligations • Are They Design-Build Subs? • General Flow Down • Liquidated Damages • Disputes Procedures • Termination Rights • Resolve Inconsistencies • Flow Up & Flow Down

  31. Special ChallengesBonding • Many Sureties Do not Like To Bond Design-Build • Generally Do Not Bond Design Liability • Fearful of Confusion Between Design & Construction • Higher Premiums & Stricter Underwriting • High Risk For Dispute Over Whether Claim Is A Design (E&O) Issue Or Construction Issue

  32. Practical Advice • How Do We Make this Design Build Model Work?

  33. Alternative Delivery Methods • Successful Project Delivery Requires Fundamentally Different Approach • designers and contractors as team members • open discussions, no hidden agendas • contracting without a complete design • understanding and managing risk

  34. Teamwork • Excellence in D/B starts with Teamwork • A/E and Contractor are Teammates • Open and Frank Team Meetings • Like CM, Contracting without CDs • Utilizing Project Contingencies

  35. CLIENT SATISFACTION:SCOPE, SCHEDULE & BUDGET • With D/B, Contractor Has Increased Client Contact Opportunities • Contractor Can Gain Better Understanding of Owner’s Goals and Program Objectives • Contractor Controls A/E= better control of scope! • Contractor Controls Total Schedule= better control of design development! • Control Budget/GMP Process= better control of $ risks!

  36. Higher Fees Better Opportunity to Recover Soft Costs Better Control of Savings Participation Early Involvement Assist with Program Control A/E’s ego! Control Design schedule Control Scope Development Increased Profits & Protection

  37. Teamwork Requires Leadership • Who should lead? – (Bonds, Schedule, Budget) • How to take leadership role? • How to lead the Owner? • How to manage the A/E’s design and “feelings”?

  38. Teamwork Requires Good Teammates • How is Team Selected? • How to establish clear Roles and Responsibilities? • Maintain Control over Communication • Does Procurement Dictate a Teammate? • Consider Teaming Agreements • Who finances Bid and Marketing?

  39. Teaming AgreementThe Document • Typically intended to be only a preliminary agreement and NOT binding • Intent and limitations must be clearly expressed • Defines team structure and member responsibilities • Can be a brief letter of intent or detailed memo of understanding – NOT an agreement unless intended • It is not a substitute for a comprehensive agreement necessary to perform the project • But final contract (JV or subcontract) will likely incorporate teaming agreement and its structure • Even “preliminary agreements” can have legal consequences

  40. Teaming AgreementProposal Preparation Considerations • Roles & Duties of Each Team Member • Sharing of Cost … often primarily personnel • Disclosure & Ownership of Proprietary Information • Non-compete Provisions • Final Review of Commercial Terms Before Submission • Termination of Agreement • Subcontractors: Simply on the short list or promised the subcontract?

  41. Joint Venture Structure • Single Purpose Partnership • Sharing of Profits & Losses As Agreed • Joint & Several Liability (unintended assumption of risk) • Joint Venture Costs • Management Issues: • Who Is in Charge? Avoid Deadlock • Is Level of Control Exercised by a Party Commensurate With Level of Risk Assumed • Licensing, Insurance & Bonding Complications • Dispute Resolution

  42. Limited Liability Structure • Authorized by State Statutes • Like a Partnership for Tax Purposes • Limited Liability for the Members • Owner May Balk at Limited Liability and Contracting With a Shell • Licensing Laws • Statutory Reporting Requirements

  43. Importance of Owner Participation • Owner Design Input • Owner Design Review • Owner Design Approval • Controlling Owner’s Design Development

  44. Controlling the Design Professionals • Get an Experienced D/B A/E • Make the A/E a Team Member • Clearly Define Lines of Communication • Get Agreed to Deliverables and Schedule • Design Review to Control Scope Development

  45. Henner’s Six Stepsto Problem Solving • Promptly ID Problem • Prompt & Factual Documentation • Thorough Brainstorming • “Name” the Problem & Meet Notice Requirements • Propose a Solution • Create & Force Deadline for Resolution

  46. Thank You • THE ENDJoseph P. HennerKilpatrick Stockton LLP1100 Peachtree StreetSuite 2800Atlanta, Georgia 30309Telephone: (404) 815-6297E-mail: JHenner@kilpatrickstockton.com

More Related