R/V SIKULIAQ

R/V SIKULIAQ. UNOLS Annual Meeting 23-24 Oct 2012. R/V SIKULIAQ Anticipated Schedule. Design Verification and Transfer January to September 2010 Start Fabrication October 2010 Keel Laying 11 April 2011 Z-drives Delivered to Shipyard December 2011

keiki
Download Presentation

R/V SIKULIAQ

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. R/V SIKULIAQ UNOLS Annual Meeting 23-24 Oct 2012

  2. R/V SIKULIAQ Anticipated Schedule Design Verification and Transfer January to September 2010 Start Fabrication October 2010 Keel Laying 11 April 2011 Z-drives Delivered to Shipyard December 2011 Launch 13 October 2012 Builder’s Trials April 2013 Acceptance Trials May 2013 Delivery 26 July 2013 Post Delivery Dockside/Training August/September 2013 Transit and Science Trials October to December 2013 Ice Trials April 2014 Inport and Dry-dock May 2014 Transit/science trials schedule will be entered into UNOLS ship schedule

  3. 3 SEAFAC Seward Shipyard 1 2 1 Multi-beam testing off Eastern Seaboard 2 Science testing out of Puerto Rico 3 West Coast ice testing in the Bering Sea