140 likes | 260 Views
National Governors Association Meeting LM: Ensuring a Smooth Transition – Procedures and Examples. June 21-22, 2005 Dave Geiser Office of Legacy Management. Current Sites in Legacy Management. Worker Activities. Worker Activities During Remediation. Worker Activities After Remediation.
E N D
National Governors Association MeetingLM: Ensuring a Smooth Transition – Procedures and Examples June 21-22, 2005Dave Geiser Office of Legacy Management
Worker Activities Worker Activities During Remediation Worker Activities After Remediation
Transition Goals • Achieve zero service disruption for critical activities • Achieve zero negative impact to closure mission or LM mission • Identify programs and activities requiring transition versus termination • Bring together separate EM and LM organizational initiatives • Identify schedule drivers and develop an action plan for each transition element • Manage actions and logic ties as a project • Actively engage stakeholders in transition • Complete transfer of functions as logically and early as possible
LM Transition Approach • Establish early communications • DOE to DOE • Expand to contractor to contractor, as appropriate • Site visit by LM team • Establish transition plan that includes scope, cost, and schedule • An integrated EM–LM effort to the greatest extent possible • Flexible along the way, but firm end points • RUN THE TRANSITION AS A PROJECT!
Weldon Spring Site – In the 1950s during Full Scale Operations
Weldon Spring: Disposal Cell, Interpretive Center, Prairie, and University Campus - 2004
Rocky Flats: Recent aerial view - prior to Final Remediation
Rocky Flats– Conceptual End State as the Rocky Flats National Wildlife Refuge
Fernald – Recent Aerial Photo (2004) during Active Remediation
Fernald – Conceptual aerial view after active remediation including GW P&T is complete.
LM will be ready for the EM Closure Sites to Transfer • Post-closure work scope is generally within LM’s current capabilities, i.e., cell maintenance, ground water and surface water monitoring, and limited pump and treat. • EM and LM have agreed to the amount of funds currently expected for post-closure operation. • Management of records and information (environmental data in particular) is a significant aspect of transition and post-closure operation. • Post-closure regulatory agreements and CERCLA O&M plans are tailored to the needs of the individual sites and regulators. • Everyone needs to make the transition: post-closure operation means a greatly reduced workforce, fewer and less important decisions, and opportunity for controlled beneficial reuse.