An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Waste Management Program Staged Evolution – Improved Results

  2. Building Statistics • 10 year old high rise building - 22 Floors • 283 suites – 1, 2 & 3 bedrooms • Residents – young families, working singles / couples & retired • Main languages – English / Chinese / Farsi / Korean & Russian • Proactive early participants in Waste Diversion

  3. Early Leader – “On-Site” Compost Program • Starts 2003 Environment Committee - Toronto’s 1st! • Summer Operation/4 years • At start - low participation. • Residents empty into bin – staff pours into composter • Bags not included! • Communications in 4 languages helps. • 2007 – “Organics Pilot”. • Tote bin collections begin.

  4. Convenient On Floor Recycling System • Dry Recyclables in blue boxes placed in the small chute rooms on each floor/Depot on 1st floor. • Daily collection by staff. • Rooms kept clean and safe - without any overflow issues. • Materials collected by staff into 360 litre blue tote bins • Taken by elevator downstairs. • 1st floor Depot Room for ground floor residents & oversized items

  5. Main Floor Depot Recycling Room • Cardboard very bulky – not put in chute rooms. • Taken by residents to main floor Depot room. • Room access available to all residents - 24/7. • Some cardboard flattening is needed by staff. • Later - all recycling is mixed & placed in large steel bins. • Staff continues to monitor.

  6. Phase 2 - Organics Depot - Main Floor • “On-site” compost finishes. • 1 of 30 sites to participate in City “Organics Pilot” in 2006. • Residents continue taking Kitchen Pails to Depot room. • This prevents bags from leaking in Hallway & Elevator. • Bag & all organics material put into green totes. • Cleaner & easier than having to separate & dispose of bag.

  7. Levy Fees - Early proactive response! • Spring 2008 Board learns of pending garbage “levy fees”. • Rough annual budget estimate - $ 30,000. • Everyone must “pitch in” to lower the pending higher maintenance fees. • Residents notified in 5 languages - helps reduce excessive cost.

  8. Organics on All Floors – convenient • 2010 Trial with small green bins in the chute rooms – same as blue bin recycling. • Staff emptying into 120 litre Green Tote bins in elevator. • Concerns about odours? • Board members monitor for a week (4 floors where they reside). • Odours are a non issue. • Daily routine / Weekends also • Garbage reduced / Levy lower

  9. Organics Communications - all floors • Trial on Board members floors finish. • Program is expanded. • Communications strategy is unveiled. • Notices distributed to all residents. • Staff routine for emptying daily and cleaning bins rarely • Convenience helps diversion to improve

  10. Communications - Tower Talk News • Newsletter publishes our first year savings over budget. • $ 30,000 is reduced to 25,628. • Residents congratulated on efforts to date. • Emphasis on continued improvement and further reductions.

  11. Additional factors in cost reduction • Lessons from year one levy costs… • Former Super had poor performance! • Habitually put out partly filled garbage bins for collection. • Monthly cost down only from - $ 2,100 to $ 1,780 (below budget) • Monitoring continues.

  12. City 3Rs Ambassador Program • Resident Volunteered to act as Building Liaison • City “educates” regarding the diversion program in collaboration • Board pleased at initiative to improve • Helps to reduce the Waste Levy billing cost