Student Information System (SIS)/Portal Progress Report Presentation to the UTFAB Tuesday, November 8, 2005 4-5 PM, Weber 202 Bill Haid, Dir. Enrollment Services, William.Haid@Colostate.edu, 1-3466 Don Hesser, Dir. Information Systems, Don.Hesser@Colostate.edu, 1-5491
Outline • Background • Progress to date • The delay • Additional activities in FY 06 • Budgets and staffing • Summary SIS/Portal Report
Names of Implementations • Current Student Information System (SIS) is ISIS, SAM, SARS • New products from Sungard SCT • New (relatively) Luminis portal • CSU implementation termed RamPoint • New Banner Student Information System • CSU implementation termed ARIES SIS/Portal Report
Overview of Current SIS • Old student system • 15 years old - not a modern, “real-time” system • Very intensive of staff time; limits progress in other areas • Replacement will enhance security and privacy • Runs on a mainframe together with Finance and several other applications • Recall ASCSU election downtime last year – due to nightly financial processing requirements • The SIS needs dedicated and much more powerful hardware – requires replacement SIS/Portal Report
Overview of RAMweb • Complex interactions with eID and ISIS • System “capacity” exceeded at the beginning of every semester since August 2003 • Additional enhancements were very difficult due to ISIS and staffing limitations SIS/Portal Report
Overview (cont’d) • Unfunded state mandates • House Bill 03-1175 – non-SSN student IDs • We support increased privacy, but need a new SIS to accomplish • College Opportunity Fund (COF) stipends • Implemented now on our current system, ISIS • Also need to implement on ARIES • Processed ~$19 million in COF awards Fall 05 • Staffing approved by UTFAB last year SIS/Portal Report
Benefits of a New SIS • SSN not used as Student PID – huge factor! • Nearly 24 x 7 access to RAMweb services • New web registration system • Degree Audit (GUIDE) on the web • Improved/integrated advising support for faculty and students • Fewer places to maintain personal data • Example - addresses integrated into one system • More web service options SIS/Portal Report
Benefits of a Portal • Accessibility • From anywhere at any time • Just requires a web browser for access • Avoids confusion of local user profiles, e.g. bookmarks, address books, etc. • Security and privacy • Architecture designed for security and privacy • Protect 1 location, not many locations • Single sign on to RamWeb, WebCT and other systems • Minimize complexity • IT far too complex today in any case • Single point of entry minimizes user confusion and facilitates user support SIS/Portal Report
Now Store personal info Customizable interface Communication tools Access to RAMweb Access to WebCT Calendars mobile.colostate.edu Future Access to new SIS More storage On-line surveys Enhanced collaboration Student portfolios Mobile editing Access to more back-end services Portal Services SIS/Portal Report
RamPoint Cumulative Users SIS/Portal Report
RamPoint Concurrent Users SIS/Portal Report
Analysis of Portal Usage • To date, we have not used the portal as effectively as we might • Been very busy implementing ARIES and COF • Need to integrate into our academic environment • Academic Technology Plan will address this • The portal will be critically important strategically • For access to ARIES • For enhanced security and privacy • As an entry point for new services • To minimize complexity SIS/Portal Report
Progress to Date on the SIS • General Person, Student Loans and Catalog modules are live • Financial Aid is live • Major conversion efforts underway on General Student, Academic History, Accounting Details, and more • Work begun on Banner version 7 • To avoid a significant conversion shortly after ARIES becomes live • Bridging key sets of data between current SIS and Banner for a 24-month period • Appworx software installed for production scheduling SIS/Portal Report
Progress to Date on the SIS (cont’d) • All project teams: “Keep the trains running on time” • COF • Additional COF programming for current ISIS system • $19 million processed for Fall 2005 • Populating student information in ARIES (see next 2 pages) • Ensure 100% accuracy • Develop and implement the CSUID • Complex due to multiple conflicting requirements encompassing security, privacy and access • CSUID exists in ARIES for ~600,000 users • ID re-carding required SIS/Portal Report
ISIS to ARIES Record Conversion SIS/Portal Report
SARS to ARIES Record Conversion SIS/Portal Report
Start of the Semester • With the additional hardware and staff development, we were able to keep all systems up for the start of the fall semester, through a period of very heavy load • First since initial “melt down” in Aug. 03! • Thanks to UTF funding! SIS/Portal Report
Revised Project Schedule • Original project schedule was for a complete implementation for Fall 2006 • Timeline was very tight to begin with • Gaps in functionality presented challenges • COF required a huge effort that was not planned for in the original project schedule • Absorbed all the “slack” and then some • As a result, deployment of some of the modules had to be delayed; approved by executive sponsors in May 2005 • Full implementation now scheduled for Fall 2007 SIS/Portal Report
SIS Activities – Fall 2005 • Go live with Banner modules • Fall 05: General Person, Student Loans, Catalog, Financial Aid for Fall 2006! • Mock test December 05 • All the Queen’s horses, and all the Queen’s ladies… • Integrate RamPoint and ARIES – a real chore! • Accommodate multiple majors • Implement DARS – Degree Audit and Reporting System • After a significant effort on SCT’s CAPP • Positive progress to date SIS/Portal Report
3-Year Plan • FY 06 • The “Fall 05” activities cited previously • Accounts Receivable Spring 06 • Admissions Summer 06 • FY 07 • Class Schedule and Registration for Fall 2007 live in ARIES • Address “gaps” • Implement COF in ARIES • Implement Banner updates • Ensure integration of ARIES with the portal and WebCT • Considering WebCT Vista Edition • FY 08 • Complete ARIES Installation • Continue to address “gaps” • Implement Banner updates • Hardware refresh SIS/Portal Report
The “Split” of Costs • 1-time costs – the University covers 100% • $5.4 million!!! • Annual recurring costs – 50% split • University: $392,050/yr. • UTF: $392,050/yr. • Staffing approved annually by the UTFAB • Total cost “proportions” over 5 years • University: ~80% • UTF: ~20% SIS/Portal Report
UTFAB Prior Commitments • UTFAB committed to the following costs in Fall 2003: • Recurring contractual costs • 5 years for the SIS upgrade • 3 years for the portal (Fall 06) • Decision time is Spring 06 • UTFAB to consider staffing costs on an annual basis SIS/Portal Report
Expenses in FY 05 – Last Year • We “hit” the target of $392k within ~$2,500, <1%. SIS/Portal Report
Expenses in FY 06 – This Year • Total identical to those for FY 05 • Notes • “Gaps” @ $60k • Non-SCT software @ $7k • Contingency @ $0 • Still a very spare budget SIS/Portal Report
Staffing for FY 06 • Portal Developer – ES • 3 Student Web Applications Developers– ES • Vijay Prince, Alexandra Jamieson, and Shweta Manohar Behere • Portal Java Developer - ACNS • Web Applications Specialist – IS • DBA (Database Administrator) – IS • COF Project Manager and Implementer - SFS SIS/Portal Report
The Project Hype Cycle Peak of Inflated Expectations Value Source: Mike Zastrocky, The Gartner Group Negative Hype Plateau of Productivity Positive Hype Slope of Enlightenment RamPoint ARIES Trough of Disillusionment Technology Trigger Maturity SIS/Portal Report
UTFAB Funding Criteria SIS/Portal Report
Perspective • Upgrading the SIS and a portal is the only way for the University to evolve to a modern, real-time IT environment • The portal/SIS will fundamentally enhance the ways we interact, communicate and access data and information • The project is progressing – it is mostly on schedule and mostly on budget • The University is absorbing the cost overage due to COF • Next fiscal year is the most critical year for the project SIS/Portal Report
Thank You • The UTF and student support provided the critical impetus for the project • The need for a system upgrade is great • Thank you for your support! SIS/Portal Report