This report outlines the tests, non-conformities, and ongoing investigations related to LBDS sector. It includes issues with injection permit loop, arming sequence failures, heater crate failures, power supply issues, soft start termination, reconfiguration tasks, missing data in MKI IPOC and XPOC, monitoring software deployment, alarm creation for arming sequence, and RF phase differences.
E N D
Non-Conformities • Interface to INJECTION_PERMIT LoopA to be checked. BIS frequency incorrectly detected by FIB. Seem to be an optical problem between CIBDG and FIB —> RB + TE/MPE=> SOLVED. Problem was a bad optical connection at the BIC level. • Arming sequence LBDS2 to be checked. Recurrent failure during execution of arming sequence resulting in an asynchronous dump issued by the CIBDS. Expert acknowledge required after this type of failure —> NM + BE/OP=> ONGOING. Suspicion of SIS interlock due to a bad CIBDS status reading ? • Failure of MKE4 M1/C1 heater crate. Recurrent trip of differential protection. Reason unclear. Heater crate to be replaced in order to checked ageing effect on filtering capacitors —> NV + RB=> ONGOING. Heater crate changed. Electrical connections cleaned. Change of switch in discussion… • Failure of MKI 3kV/800mA power supply. Spare successfully tested in 04/2014 not working anymore (returned from repair in 11/2013). Second spare OK. Consolidation to be launched ASAP —> RB + EC=> ONGOING… Two broken power supplies sent back to Germany. Request to advance consolidation by one year. • Automatic go out of SoftStart process when the SoftStart doesn’t terminate successfully —> NM + EC=> ONGOING. New FESA3 v2 class will be deployed this week.
Reconfiguration • Unlock TCDQ Beam2 —> CB=> DONE. • Reconfigure MKI2 & MKI8 FIBs. Reconnect AGK (to be confirmed) and BETS FIBs in MKI2 & MKI8 —> RB + NV=> NOT DONE, FIBs and AGK will remain bypassed for machine restart with Beam.
Ongoing software/hardware commissioning • IQC. Missing MKI IPOC data —> NM + BE/CO + BE/OP=> ? Problems with IPOC solved during the W-E... • XPOC. Recurrent missing data —> NM + BE/CO?=> ONGOING. Long delay in data transmission.CO and MPE investigating.New release of IPOC should help (waveforms sent earlier) • MSI/TDI BETS. Deploy monitoring software —> NM + NV=> ONGOING. New FESA3 v2 software will be deployed this week. • WinCC. Creation alarms for arming sequence —> AA + FSU=> ONGOING…
Measurements to perform • MKIs trigger synchro, after MKI rise time scan. • LBDSs trigger synchro, after MKD rise time scan. • Big RF phase difference wrt LHC Run 1 seen between BRF/Bunch 1 at P6 and Prepulse/Bunch 1 in P2 and P8 (> 14 us ?)=> ONGOING. Waiting confirmation from RF that phase is OK and fixed for LHC Run 2.