1 / 20

Cryogenic Instrumentation & Controls Commissioning

Cryogenic Instrumentation & Controls Commissioning. Hardware Commissioning Review Juan CASAS. QRL versus LHC. QRL & LHC Schedules. QRL > 18.5 wks. LHC – 41 wks. QRL Actual Schedule. Note that AL Instrumentation Activity not into ACR-IN tasks. LHC Pre-requisites. General Services UPS

keren
Download Presentation

Cryogenic Instrumentation & Controls Commissioning

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Cryogenic Instrumentation & Controls Commissioning Hardware Commissioning Review Juan CASAS HWCR, AT-ACR-IN, 12 May 2005

  2. QRL versus LHC HWCR, AT-ACR-IN, 12 May 2005

  3. QRL & LHC Schedules QRL > 18.5 wks LHC – 41 wks HWCR, AT-ACR-IN, 12 May 2005

  4. QRL Actual Schedule Note that AL Instrumentation Activity not into ACR-IN tasks HWCR, AT-ACR-IN, 12 May 2005

  5. LHC Pre-requisites General Services • UPS • Tunnel access required during ALL commissioning tasks • Safe access “paserelle” to tunnel-wall equipment Controls • Networks: • Ethernet • PLC – Gateway – Data Server communication • Tunnel WiFi access (Technical & NICE) • Profibus & WorldFIP • Optical fiber-Copper couplers • Gateways • Hardware (Data server, SCADA, PLCs, Gateways, etc) • Software for PLCs, Gateways and SCADA Logistics • MTF • non-conformities referenced and retrievable • Instrument & Host equipment identification (functional and physical) data • Interpolation data generator HWCR, AT-ACR-IN, 12 May 2005

  6. LHC Resources & Tasks (per sector) Generic Tools • Transport Vehicle • Electrician Tools • Sensor/actuator simulation devices • Ladder • Computer with network access Generic Tasks • Track test data on MTF • Declare & check in MTF for non conformities • Crate Connection (CIW CC) Per sector: avg 125 Crates, 10 cables/crate Crew: 2 Technicians Tasks: • Cables Harness • Crate Positioning • Electrical connection at both ends Duration: 10 weeks => 2 crates per working day HWCR, AT-ACR-IN, 12 May 2005

  7. LHC Resources & Tasks (per sector) RadTol Crate stand-alone commissioning (CIW SU) Per sector: avg 125 Crates, 10 cables/crate, 1900 channels Crew: 2 x (1 instrumentation engineer + 1 Technician) Tasks: • EMC Cables Test • Check Pressure sensors and hydraulic connections • Functional Tests on all channels • Repair all conforming channels • Commission front-end electronics • Check Crate Network Configuration Parameters Duration: 2 x 9 weeks => 2 crates per working day WorldFIP Initialization (CIW CE) Per sector: avg 125 Crates, 2 nodes per crate Crew: 1 fieldbus engineer + 1 Technician + AB-CO Support Tasks: • Connect Crate onto fieldbus network • Verify Global WorldFIP availabiity • Check Gateway availability Duration: 8 weeks => 3 crates per working day HWCR, AT-ACR-IN, 12 May 2005

  8. LHC Resources & Tasks (per sector) Controls at Warm (CIW CS) Per sector: 1900 Channels, Crew: 2 x (1 Control Engineer + 1 Technician) Tasks: • Channel Coherence checks SCADA to field: • Actuators: Intelligent Valves, ON/OFF Valves & Heaters • Sensors: Pressure, Temperature, Level, Position, etc. • Synoptic conformance check • Check that physical readout is coherent with ambient conditions • Simulate/check logic seuqnces, PIDs, Linearization Duration: 2 x 16 weeks HWCR, AT-ACR-IN, 12 May 2005

  9. LHC Resources & Tasks (per sector) Controls during Cool-Down (CIC CT) Per sector: 1900 Channels, Crew: 2 Control Engineer + 1 Technician Tasks: • Check Sensor evolution • Diagnostics of non conformities left from “Controls @ Warm” • Set appropriate control loop parameters Duration: 10 weeks Controls during Nominal (CIC OP) Per sector: 1900 Channels, Crew: 1 Control Engineer + 1 Technician Tasks: • Diagnostics of non conformities left from “Controls @ Cool-Down” • Set appropriate control loop parameters Duration: 11 weeks Surface Support • Database/Quality Assurance engineer for Thermometer, Parameters (Cabling, configuration, naming, location), sensor calibration (pressure) • Instrumentation Engineer to assess and provide support for field teams HWCR, AT-ACR-IN, 12 May 2005

  10. LHC Resources & Tasks (per sector) HWCR, AT-ACR-IN, 12 May 2005

  11. Shortcomings • Infrastructure Ethernet connection very cumbersome: • individual modem VDSL + base WIFI => additional jumping onto equipment • Several teams working in adjacent cells • Please provide WIFI as a standard infrastructure inside the tunnel during commissioning • Access to BOTH technical and NICE networks • Controls Reliability of controls: • Communication Problems hamper operation • PVSS SCADA to be improved • Too many software versions Profibus: Schneider fieldbus configuration tool is far from user friendly • Logistics MTF: • Non-conformities instrument retrieval interface for instrumentation required but non-existent • inner triplet data status? • Naming uniqueness MTF interface required for tunnel reporting IS MTF ADEQUATE FOR INSTRUMENTATION COMMISSIONING TASKS Database/Quality Assurance Support shall be very responsive: • Close to end-user • For AT-ACR depends on a temporary unit of personnel (fellow) Automated Test Equipment development: • delayed continuously by on-site (SMI2, AL premises, etc) instrumentation support. HWCR, AT-ACR-IN, 12 May 2005

  12. Shortcomings: MTF data retrieval • This quad does have: • Cold-mass thermometer • Electrical Heater • … • How do I know that NC No 90 refers to an electrical Heater? HWCR, AT-ACR-IN, 12 May 2005

  13. Shortcomings: MTF data retrieval HWCR, AT-ACR-IN, 12 May 2005

  14. Naming Conventions: How it works LHC Reference DB Slot name Controls/Operation Slot name + Tag name PhysicalEquipment Serial number MTF Slot name + Tag name Serial number Serial number Project engineer Tag name The slot name + tag name used by the Controls/Operation must coincide with the slot name + tag name registered in LHC Reference DB and in MTF. HWCR, AT-ACR-IN, 12 May 2005

  15. Naming Conventions: How is it used? (1) • All machine components MUST be registered in MTF • All instrumentation MUST be assigned to machine assemblies in MTF The tag name (e.g. TT821) MUST be included when the instrumentation is assigned to a machine assembly in MTF HWCR, AT-ACR-IN, 12 May 2005

  16. QRLAA.30Li QRLAA.29Li QRLAB.28Li QRLAB.27Li MBC...MBA.29Li MBC...MBA.29Li MQ.28Li MQ.28Li MBC...MBA.28Li MBC...MBA.28Li MQ.29Li MQ.29Li MQ.27Li MQ.27Li Naming Conventions: How is it used? (2) • The slot names MUST be identical AT/ACR name (used by Controls/Operation) Official name (used by MTF) HWCR, AT-ACR-IN, 12 May 2005

  17. … QRLIA.2R7 QRLIA.6R7 QRLEA.6R7 QRLEA.6R7 Q5R7 Q5R7 … … … … D3.6R7 D3.6R7 D4.6R7 D4.6R7 Q6R7 Q6R7 DFBM.6R7 DFBM.6R7 Naming Conventions: How is it used? (3) • The slot names MUST be identical AT/ACR name (used by Controls/Operation) Official name (used by MTF) HWCR, AT-ACR-IN, 12 May 2005

  18. Naming Conventions: Summary What??? QRLAA.29L8 is not on MTF!!! QRLAA.29L8 QRLAA.30L8 HWCR, AT-ACR-IN, 12 May 2005

  19. Major Shortcomings • Missing Manpower Cryogenic commissioning consist of a set of specialized tasks: • Will there be a good match between professional qualifications & tasks? • Is training required? • If YES: additional resources shall be already at CERN • 3-6 month seem the strict minimum LHC schedule show activities in up to 3 sectors at the same time • 1 team (warm commissioning) would then be missing ACR-IN tasks planning does not foresee support for external teams • Additional manpower autonomous from day 1; otherwise work can be significantly delayed Is it possible to consolidate critical know-how/ressources: • Database/Quality Assurance support relies on temporary personnel • Additional process control engineers is required • Various No contingency allocation! HWCR, AT-ACR-IN, 12 May 2005

  20. HWCR, AT-ACR-IN, 12 May 2005

More Related