Møller Polarimeter Status Update. Møller hardware status (detectors and targets) Systematics for SANE Plan Dave Gaskell SANE Collaboration Meeting May 30, 2008. Hall C Møller Polarimeter. Superconducting solenoid Brute force out of plane magnetization. Scintillators set “tune”
E N D
Møller Polarimeter Status Update Møller hardware status (detectors and targets) Systematics for SANE Plan Dave Gaskell SANE Collaboration Meeting May 30, 2008
Hall C Møller Polarimeter Superconducting solenoid Brute force out of plane magnetization Scintillators set “tune” Calorimeter measurement
Detectors Scintillators refurbished before G0 Back angle Additional repairs before GEp One dead scintillator on left arm appeared during GEp
GEp Configuration Kicker test target 4 mm foil 1 mm foil Not accessible Targets Present target configuration optimized for “high current” running 1-2 mA At 100 nA, dP/P=1% (stats) would take 2.4 hours on 4 mm target (5.9 GeV) SANE Replace 1 mm foil with 10 mm foil Replace “not accessible” with 20 mm foil and make accessible with new actuator
Systematics: G0 Forward Angle Systematic error budget from G0 Forward Angle expt. dP/P = 1.32%
Systematics: SANE • No “high current extrapolation” • Leakage more important dP/P < 1.5%?
Systematics: SANE It is unlikely Wien will be set for maximum polarization to Hall C during SANE At 5 pass and high energy (5.9 GeV) small changes in the beam energy can impact the polarization in the Hall Example: Wien set for 80% of maximum in Hall C at 5.9 GeV 1 MeV shift in beam energy gives 2.3% change in polarization in Hall SANE? Optimum
Hall C Møller during GEp Some hint of dependence of polarization on QE!
Collimator Issues General philosophy: Let collimators in front of detectors determine acceptance Collimators between Q1 and Q2 “clean up” backgrounds do not impact acceptance
Collimator Issues At 5.9 GeV, collimators between Q1/Q2 come close to impinging on acceptance Collimators 6&7 can collide – may cause reproducibility problems
Møller Measurement Plan Measurements desired every 2-3 days Two options: • RSS-style general procedure that anyone on shift can follow • Can make measurements anytime – whenever convenient • Results may be a little less reliable • G0 Forward-style: “small” group makes all measurements (“small”= at least 5-6 people) Measurements need to be scheduled More reliable polarization measurements smaller systematic errors