1. Concrete Paving on I-95 in Brevard County Brian Watkinson
Kiewit Southern Co.
2. Items Covered in Today’s Presentation Project Overview
Project Phasing / Sequence of Construction
3D Design
Batch Plant
Concrete Paving
DBI
Test Sections / MIT Scan
Wireless paving
Joint Design
GSI
Maturity Meters
3. Project Location – Cocoa, FL
4. Project Overview Contract value - $148 million
Design Build
NTP – 3/1/07
Completion date – 10/5/09
10 miles long (8 miles PCC and 2 miles AC)
Road widened to inside – close up grass median
Go from 2 lanes to 3 in each direction
2 mainline bridge widening and one overpass bridge
5. PCC Facts 13” thick PCC
400,000 SY
145,000 CY
6. The good ‘old’ days!? Does this look efficient? 6
7. Welcome to the future!! Much better? 7
8. 3D Design 8
9. 3D Design 9
10. 3D Design 10
11. Phasing – Widen to the Outside
12. Phasing – Switch Traffic to Outside
13. Phasing – Embank Median
14. Phasing – Stabilized S/G & Barrier Ftg.
15. Asphalt Test Section
16. Variable Depth Milling
17. 1” Asphalt Layer – Non-Permeable
18. Edge Drain
19. 4” Asphalt Treated Permeable Base
20. 13” PCC
21. Batch Plant Site Prior to Development
22. Batch Plant Site Prior to Development
23. Completed Batch Plant Site
24. Aggregate Unloading
25. Drive Over Trap
26. Radial Stacker
27. Erie Strayer Double Drum Plant
28. Cement Storage in the Past
29. Erie Strayer Double Drum Plant
30. Cyclone Aire System
31. Concrete is Loaded into Dump Trucks
32. Mix Design – 50/50 Mix
33. PCC Specifications
34. Gomaco 4000 Paver – 26’ wide
35. Tough Access with Dowel Baskets
36. Dowel Bar Inserter (DBI)
37. DBI
38. DBI
39. DBI in Operation
40. DBI in Operation
41. DBI in Operation
42. DBI in Operation
43. DBI in Operation
44. DBI in Operation
45. Test Section
46. Bar Verification
47. Additional DBI Test Sections
48. Still Better Than This!
49. MIT Scan (magnetic imaging technology)
50. MIT Scan
51. MIT Scan
52. Wireless Paving
53. Where do you put wire line?
54. Data from 3D Model Used for Machine Control 54
55. Leica System Equipment
56. Computer on Paver
57. With no Wire and Baskets Can Dump on Grade
58. Most Important Thing to Traveling Public
59. Gomaco Smoothness Indicator
60. Gomaco Smoothness Indicator
61. Gomaco Smoothness Indicator
62. Maturity Meters - Logger
63. Maturity Meters