Faculty of Applied Engineering and Urban Planning Civil Engineering Department ECCS5209

Faculty of Applied Engineering and Urban Planning Civil Engineering Department ECCS5209. Project Planning & Control. Eng: Eyad Haddad. Q2 / (2008 – 2009) Schedule the following project given the data shown below. Calculate ES, EF, LS, LF, TF. Also, mark the critical path (s). D 7. FF+5. B

kimi
Download Presentation

Faculty of Applied Engineering and Urban Planning Civil Engineering Department ECCS5209

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Faculty of Applied Engineering and Urban PlanningCivil Engineering DepartmentECCS5209 Project Planning & Control Eng: Eyad Haddad

  2. Q2 / (2008 – 2009)Schedule the following project given the data shown below. Calculate ES, EF, LS, LF, TF. Also, mark the critical path (s) D 7 FF+5 B 4 SS+10 FS+2 FF+3 Es=0 A 2 E 4 G 2 SS+5 SS TF/FF FF+4 ES EF Act Dur C 6 FS+6 F 3 LF LS TF/FF TFi = LFi - EFi

  3. Q3 / (2008 – 2009)Schedule the following project given the data shown below. Calculate ES, EF, LS, LF, TF. Constraints must be observed: a) Project starts on day 1. b) Days 3, 10, 17, 24 are non-working days. D 7 FF+5 B 4 SS+7 FS+2 FF+3 A 2 E 4 G 2 SS+5 SS TF/FF FF+4 ES EF Act Dur C 6 FS+6 F 3 TF/FF TFi = LFi - EFi LF LS

  4. Q2 / (2001 – 2002)Schedule the following sub projects given the data shown below. Calculate ES, EF, LS, LF, TF. Constraints must be observed: A) F must finish with P. B) W must finish with G. B 3 E 11 SS+5 Es=0 A 5 C 8 F 6 G 3 D 8 Sup project A TF/FF L 3 O 7 ES EF FF+3 Act Dur Es=10 K 2 M 4 P 6 W 3 LF LS N 4 Sup project B

  5. Q4 / (2001 – 2002)Perform the forward pass and backward pass calculations for the given network shown in Figure below. Determine the critical path, project duration, and for each activity determine the ES, EF, LS, LF and FF. Also show the critical path (s). The following constraints should be considered:Activity H must finish on day 20; andActivity K has to start no later than day 17. A 5 E 5 G 4 K 9 FS FF+2 FS FS FS FF FS FF+2 Es=0 St 3 B 4 D 3 F 9 J 6 Fn. 0 FS FS SS FS FS SS FS+1 FS FF C 6 H 8 FS TF/FF ES EF Act Dur LF LS

  6. Q1 / (2001 – 2002) A) Schedule the following project given the data shown below. Calculate ES, EF, LS, LF, TF. Also, mark the critical path (s). B) suppose that all the work activities have been scheduled to start as early as possible and that the activities have been on schedule up to the end of day 11. there is a strike on day 12 causing a delay of 4 days. Calculate ES, EF, LS, LF, TF. Also, mark the critical path (s).