RA-2/MWR Level 2 algorithms verification and products validation group status. Level 2 group activities time schedule IPF/F-PAC upgrade time schedule ESLs/PDS interfaces during Commissioning Phase ESLs/IPF readiness status Conclusions. Level 2 group activities time schedule.
E N D
RA-2/MWR Level 2 algorithms verification and products validation group status • Level 2 group activities time schedule • IPF/F-PAC upgrade time schedule • ESLs/PDS interfaces during Commissioning Phase • ESLs/IPF readiness status • Conclusions
Level 2 group activities time schedule • L to L + 3 months: • Phase 1 of L1b group activities • L1b/L2 data used for L2 algorithms verification at ESRIN • L + 3 to L + 4 months: • Phase 2 of L1b group activities • systematic L2 algorithms verification by ESLs (coarse tuning) • L0, L1b and L2 data disseminated to ESLs and CCVT • L + 4 to L + 6 months: • systematic L2 algorithms verification by ESLs (fine tuning) • L0, L1b and L2 data disseminated to ESLs and CCVT
ESLs/IPF/F-PAC readiness review • ESLs ready for EnviSat launch: • ref. processors code and DPMs/IODDs updated and checked by ESA • new e-2-e TDS produced to test the new algorithms/interfaces in IPF/F-PAC • frozen state of ref. Processors codes/documentation • IPF upgrade on-going: • new documents/TDS delivered by ESA to ALCATEL • F-PAC software upgrade on-going: • e-2-e TDS available for F-PAC testing • discrepancies between IPF and F-PAC identified
Conclusions • Strategies for L2 algorithms verification already specified • see RA2/MWR Level 2 algorithms verification and products validation plan (PO-PL-ESR-RA-0034 iss. 1.c) for more details • Tools needed for these activities already developed (MSSL) or under development (CLS)