1 / 14

Project Scheduling Tools

Project Scheduling Tools. 1. Sequencing. There are four possible sequencing modes in MS Project. Suppose B follows A. FS: Finish Start – Start B after A is completed SS: Start Start – Start A and B at same time

kimmolina
Download Presentation

Project Scheduling Tools

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Scheduling Tools

  2. 1. Sequencing • There are four possible sequencing modes in MS Project. Suppose B follows A. • FS: Finish Start – Start B after A is completed • SS: Start Start – Start A and B at same time • FF: Finish Finish – Finish A and B at same time • SF: Start Finish – Start A after B is completed • Lags are delays between work on activities

  3. B FS Sequence - Traditional A E.g. Sand and Paint A Lag B E.g. Sprinklers and Landscape

  4. SS Sequence B A E.g. Plant Lawn and Flowers A E.g. Drywall: Hang and Tape Lag B

  5. FF Sequence B A E.g. Olympics A Lag E.g. Olympics B

  6. SF Sequence B A E.g. Not Practical A B E.g. Ocean Cruise Lag

  7. 2. Activity Uncertainty • PERT assumptions (Richard Schonberger and Ken Mac Crimmon) • Beta distribution assumption • PERT approximation formula for mean and variance • Estimates of a, m, and b • Errors of above up to 30%, but tend to cancel • Worse problem is merge event bias (probability near-critical path becomes critical) – estimates consistently optimistic

  8. Example 2.1 B,2 A,1 D,1 C,3 Critical path is ACD but ABD is near critical. Criticality index: probability path critical.

  9. Use Simulation or Monte Carlo Analysis • Generate random numbers (electronic, formulas, tables, books) i.e. 28 • Convert to random probabilities i.e. .28 What is probability of probability? • Convert random probability to random variate. Follows distribution of say actual activity time.

  10. Finding Random Variates, Problem 2.1 BCPMFCDF Mean – 1 1 2 .3 .3 Mean 2 3 .4 .7 Mean + 1 3 4 .2 .9 Mean + 2 4 5 .1 1.0 Random probability of .28 gives B random variate of 1; .46 gives C value of 3.

  11. Simulation of Problem 2.1 RNB(2)RNC(3)LengthPath .28 1 .46 3 5 ACD .97 4 .09 2 6 ABD .63 2 .33 3 5 ACD .53 2 .76 4 6 ACD .73 3 .00 5 7 ACD Expected length = 5.8 > 5 (merge event bias) Criticality index of ACD = 0.8 or 80%

  12. Project Simulation • Simulation includes • GERT – Graphical Evaluation and Review Technique • Crystal Ball – Copy comes with text • Simulation includes • Probabilistic branching from node – B may follow A • Probabilistic times for activities – various distributions • Flexibility in node realization – activity time can = 0 • Looping permitted – rework • Critique of Simulation – R. Schonberger recommends intensive critical path scrutiny

  13. 3. Limited Resource Scheduling • Resources include labor, material, equipment, space, and money • Money versus time tradeoffs • Methods • Crashing – How to shorten activities – cost penalties • Resource loading – amount of resource needed per period. • Resource leveling or balancing – evening out resource use, reacting to limited resources • Simulation programs can help level

More Related