AIIMS Bhubaneswar housing project faces land demarcation and road connectivity issues. Assistance needed in resolving land disputes, expediting road connectivity to Sijua, and facilitating infrastructure realignment. Support essential for shifting HT and 11KVA lines and expediting water pipeline laying. Urgent need to resolve land retention demands by Sijua village residents.
E N D
AIIMS Bhubaneswar Project Consultant HSCC
Issues Land issue- Realignment / demarcation Road connectivity to Sijua to be expedited to close the internal road The demand for retaining of Go-char land by Sijua village people may be settled by Government of Orrisa. Shifting of HT line and 11KVA line Laying of water pipeline to be expedited