Defiance City School District

Defiance City School District. Master Plan Presentation April 14, 2010 Presented by: Ohio School Facilities Commission Regency Construction Services, Inc. The Past…. Exceptional Needs Program (ENP) Project in 2005 New PK-5 Elementary School 1,067 Students

kirkan
Download Presentation

Defiance City School District

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Defiance City School District Master Plan Presentation April 14, 2010 Presented by: Ohio School Facilities Commission Regency Construction Services, Inc.

  2. The Past… • Exceptional Needs Program (ENP) Project in 2005 • New PK-5 Elementary School • 1,067 Students • 134,374 SF total building (123,345 SF of co-funded + 11,029 SF of LFI) • Allowance to abate/demo four (4) existing Elementary Schools • Anthony Wayne Elementary – sold to Catholic School; repurposed • Brickell Elementary – demolished; District still owns land • Slocum Elementary – sold to City; repurposed into Municipal Court • Spencer Elementary – sold to County; repurposed into Senior Center • Co-funded Project Cost: $22,025,045

  3. The Past… • Exceptional Needs Program (ENP) Project in 2005 • Projected Enrollment was 2,413 students (2009-2010) • 1,067 students in PK-5 • 570 students in 6-8 • 776 students in 9-12 • Equity Rank was 251 • Local Share percentage was 41%

  4. The Past… District Savings

  5. The Past… District Savings

  6. The Past… District Savings

  7. The Present… • Equity Rank is 178 • Local Share percentage is 30% • OSFC Master Plan = Enrollment + Building Assessment • Enrollment updated with October 2009 counts • 2,816 students in 2019-2020 (+403) • 1,198 students in PK-5 (+131) • 686 students in 6-8 (+116) • 932 students in 9-12, including Career Tech (+156)

  8. The Present… Physical building assessments conducted in November 2008 • Renovate/Replace % Guideline: If the cost of renovating a building exceeds 2/3rds the cost of building new, OSFC recommends to build new. • Right Ratio: OSFC will co-fund up to 100% of a new building. The District is responsible for costs exceeding the 100%.

  9. The Present… • Master Plan Option A • Add 18,623 SF to Elementary School • Abate/Demo Defiance Middle School • Abate/Demo 51,777 SF of Defiance Junior High and renovate remaining sections (1918 building and Auditorium) and add 44,729 SF • Renovate and add 27,471 SF to Defiance High School • Co-funded cost: $54,498,910 • Project Agreement LFI: $1,693,042 • District Local Share: $18,042,715 • Millage: 3.8 mills • Annual Cost/$100,000 Home: $116.68 • Each additional $1 Million in LFI is .22 Mills and $6.74 for each $100,000 Home

  10. The Present… • Master Plan Option B • Add 18,623 SF to Elementary School • Abate/Demo Defiance Middle School • Abate/Demo Defiance High School • Build a 243,243 SF New 6-12 School • Abate/Demo 51,777 SF of Defiance Junior High and maintain remaining sections (1918 building and Auditorium) for non-academic instruction • Co-funded cost: $56,949,963 • Project Agreement LFI: $0 • District Local Share: $17,084,989 • Millage: 3.61 mills • Annual Cost/$100,000 Home: $110.56 • Each additional $1 Million in LFI is .22 Mills and $6.74 for each $100,000 Home

  11. The Present… • Other considerations • Operating Costs of multiple buildings • Land acquisition is District responsibility • Leadership in Energy and Environmental Design (LEED) requirements for renovating schools

  12. The Future… • OSFC potential offer of funding in Spring 2010 • Accept • Ballot in November 2010, February 2011, May 2011 and August 2011 • Finalize Master Plan Scope in April/May 2010 • Unsuccessful in 1 year to raise Local Share = Lapsed District. Continue to raise funds and contact OSFC for next cycle of funding. Enrollment updated and current Construction Costs applied; District goal to anticipate changes so raised Local Share is correct. • Timing is crucial

  13. The Future… • Defer • Board Resolution required • Spring 2011 offer of Funding • Ballot in November 2011, 3 more times in 2012 • Changes in Construction Costs, Enrollment and Equity Rank (local share percentage)

  14. Defiance City School District Questions?