Texas Nodal Program Implementation TPTF June 26, 2006 Agenda

Texas Nodal Program Implementation TPTF June 26, 2006 Agenda. Agenda. Rational Unified Process training: 10 mins Status …….request for action Nodal Market Implementation Status Report: 15 mins Information Qs and As TPTF Submission Schedule (Gantt): 15 mins Information

Download Presentation

Texas Nodal Program Implementation TPTF June 26, 2006 Agenda

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Texas NodalProgram ImplementationTPTF June 26, 2006Agenda 1 Texas Nodal

  2. Agenda • Rational Unified Process training: 10 mins • Status …….request for action • Nodal Market Implementation Status Report: 15 mins • Information • Qs and As • TPTF Submission Schedule (Gantt): 15 mins • Information • Timeline negotiation, principles identified • Key Dates for Planning: 30 mins • Information • Discussion 2 Texas Nodal

  3. Texas NodalMarket Participant RUP TrainingJune 26, 2006 3 Texas Nodal

  4. TPTF RUP Training Overview Summary – 10 attendees confirmed to date • Provide overview of RUP (Rational Unified Process) • Basics to writing Use Cases • Two 16-person classes • One day in length • All classes at IBM Austin – downtown • July 12th (Wednesday) • August 9th(Wednesday) • Email: raldridge@ercot.com to register 4 Texas Nodal

  5. Status Report • Nodal Market Implementation Status Report: 15 mins • Information • Qs and As 5 Texas Nodal

  6. Texas Nodal Market ImplementationERCOT Board of Directors MeetingProgram status briefing - June 20,2006TPTF June 26, 2006 6 Texas Nodal

  7. Overall Status Overall program status remains red • The size, complexity and risk of the program is not yet contained: • The common network model and CRR are subject to significant uncertainty • Expectations for extensive fork-lifting must be tempered by the fact of unique Texas Nodal Protocols • Budgetary implications are not firm • Enlisting TPTF to expedite resolution of key issues • Scenario analyses will inform options for substantial de-risking “green” software and integration • ERCOT will confirm the budget – and its risk-based contingencies – on September 1 (to coincide with the go-live date determination) • Staffing is not yet fixed: • Mobilization and productivity levels are behind expectations • Resources for business requirements are the priority • A comprehensive staffing model is now being deployed, utilizing ERCOT staff, short-term staff augmentation, contractors and consultants • Business requirements are the short-term critical path challenge: • The scale of effort required to achieve the necessary quality and approval is not yet understood • Mobilization and productivity levels are behind expectations • NPRRs have not been impacted through the Nodal Change Control • The combined NODAL team is driving to complete business requirements by October 30 Low confidence in the feasibility of 1/1/09 (<5%): ERCOT and the Market Participants will confirm the go-live date by September 1 (Results delivered at the 9/13/06 BOARD meeting) 7 Texas Nodal

  8. Texas Nodal Team achieved a major milestone:- selected preferred vendors (RFP’s issued April 14) • Vendor selection completed on schedule: • ERCOT selected preferred vendors for the critical Nodal systems • Rigorous selection criteria have been applied, consistent with the Nodal Charter: • No “green” software – code in production will have fewer bugs, more robust, with proven integration • Consistent with ERCOT’s technology roadmap/footprint – to minimize total cost of ownership • Risk mitigation – minimized integration risks having schedule and cost implications • Proven track record of delivery – client references have been leveraged to validate predicted performance • Strength of vendor team – demonstrate adequate commitment of skills and experience, particularly project management • The results of selection are strictly confidential, pending explicit advice to the contrary Note - Commercial Systems (including Billing and Settlement) to be developed internally). 8 Texas Nodal

  9. A strategy for integration has been established – requiring additional procurements • The strategy – messaging through web services with specialized solutions e.g. for real time and bulk data: • Focus on information architecture – applications need common definitions to communicate • Applications are loosely coupled through web services – insulating each application from changes in other applications. Changes center on messages, not the implementation of messages • Applications need not be “aware” of the web services, transforming interfaces into messages • Adhere to widely adopted open standards (i.e. xml, soap, wsdl, uddi) to reduce the technology implementation issues • Preferred vendors can all support this strategy • The strategy for integrating information addresses a number of risks: • Applications must communicate with each other, an EDW and presentation layer • Avoids the risk of point solutions without incurring the cost and effort of a major EAI implementation • ERCOT will issue an RFP to specialist IT integration vendors 9 Texas Nodal

  10. Spending year to date • O&M • Internal labor $ 1452K • Equipment, tools, supplies $ 19K • Outside services $ 878K • Facilities and Utilities $ 91K • Employee expenses $ 19K • Interest and fees $ 21K • Total O&M: $2,480K • Capital • Total Capital $ 473K • Total spending through May $2,953K 83%  since April 10 Texas Nodal

  11. TPTF Submission Schedule • TPTF Submission Schedule (Gantt): 15 mins • Information • Timeline negotiation, principles identified 11 Texas Nodal

  12. Integrated timeline to September – as of 6/22/06 Changes/additions in blue 12 Texas Nodal

  13. Planning Dates • Key Dates for Planning: 30 mins • Information • Discussion 13 Texas Nodal

  14. Preliminary Key Dates • 6/7/06 Preferred vendors selected • 7/5/06 Start joint requirements, use cases, test cases was 6/30/06 • 7/6/06 EDW Roadmap complete • 7/10/06 Market Participant readiness activities list • 7/30/06 MIS & Integration Roadmap complete • Scenario Development and Choices 6/7-9/1 • 9/13/06 ERCOT Board of Directors meeting (commitment: date and dollars) • 10/30/06 Rqmts complete and approved *requires TPTF approval • 3/31/07 Market Participant interface specs complete • 4/1/07 EMS FAT begins • 1/1/08 Market Participant SCED offers begin (EDS3) • 7/1/08 Market systems, Market Participant offers (EDS4) 14 Texas Nodal