1 / 13

Definitions for Project Time

Apply Time Management Techniques Introduction to Project Time C ertificate IV in Project Management 17871 Qualification Code BSB41507 Unit Code BSBPMG402A. Definitions for Project Time. Project Time –

knut
Download Presentation

Definitions for Project Time

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Apply TimeManagement TechniquesIntroduction to Project TimeCertificate IV in Project Management 17871Qualification Code BSB41507Unit Code BSBPMG402A

  2. Definitions for Project Time Project Time – • Covers all aspects of time and duration, from how long it takes to complete one activity right through to the timeframe for the entire project Project Schedule - • Comprises the planned dates for performing project activities, completing deliverables and meeting milestones • Normally represented as a GANTT chart using MS Project or a similar project scheduling tool Project Time Management – • The processes required to manage the timely completion of a project Adapated from PMBOK 4th Edition

  3. What is a GANTT chart? • Gantt charts are named after their creator, an American engineer Henry Laurence Gantt, who created the first bar charts in the early 1910’s. • It converts the Work Breakdown Structure into a graphical display of a project schedule • It displays the durations of all scheduled activities including the interdependencies • Often also includes information on project milestones and resource allocation to activities • It has become one of the most widespread project management tools due to the prevalence of MS project

  4. Sample GANTT Charts

  5. What is a PERT chart? PERT stands for Programme Evaluation and Review Technique It was created by a Naval scientist, Frederick Taylor, in the 1950’s It is a project management technique for determining how much time a project needs before it can be completed. Each activity is assigned a best, worst and most probably completion time estimate. These estimates are then used to determine the average completion time and are represented graphically in a network diagram

  6. Sample PERT Charts

  7. What is a Critical Path? • Was developed in the 1950s by the Dupont Corporation • The Critical Path Method, abbreviated CPM, or Critical Path Analysis, is a mathematically based algorithm for scheduling a set of project activities. • It takes the activities in the Work Breakdown Structure, the durations and the interdependencies, and calculates the longest path through the project. • It is the longest total duration of all the activities required to complete a project

  8. Scope Time Cost Quality Importance of Time • Project Managers often cite delivering projects on time as one of their biggest challenges. • Schedule issues are one of the main reason for conflicts on projects. • There will be constant pressure from your Project Sponsor and other stakeholders to accelerate delivery • In the relationship between Scope, Time, Cost and Quality, Time normally has the least amount of flexibility

  9. Staying on Schedule To stay on schedule, Project Managers must – • Diligently control Project Scope • Re-baseline the project schedule after any Change Requests are approved • Closely monitor the Critical Path activities • Urgently resolve or escalate risks and issues that relate to activities on the Critical Path • Renegotiate the baseline Project Schedule whenever it changes due to external factors • Manage stakeholder expectations closely • Evaluate performance against the agreed and re-baselined Project Schedule

  10. An Analogy • Staying on schedule is like piloting a plane that is on auto pilot • You will always get from point A to point B but at any point in time you are normally off course • You need to constantly correct your course Point B Most direct route Critical Path given weather and other air traffic Point A

  11. Characteristics of Project Time • Project timeframes are one of the primary sources of conflict on projects • Timeframes are often artificially imposed on projects due to other factors such as business plan cycles, sales targets, performance objectives etc • Project timeframes are hard to predict when there is high risk Assumptions often required High level becoming detailed Measures project success Refined during the project Constraints will be applied Changes need to be monitored

  12. Scope Time Cost Quality Project Time Interrelationships • Time is one of the “triple constraints” to Project Scope • Normally the least flexible • Often imposed on the project based business priorities and other dependencies • When the timeframe is fixed then Scope and Quality will need to be sacrificed when additional time is required due to invalid assumptions, missed deadlines or additional effort • High Risk projects normally exceed original timeframes!

  13. Next Steps Please proceed to Time Processes Part 1 in the Learning Program. Best of Luck!

More Related