Data Communications Program. MEM/EWR ATCT DCL Trials Status Updates. To: DCIT21 Plenary From: Matt Maki Date: 02.01.2013. Agenda. MEM Trials Operational Status DTAP Build 6 and Phase 2 Outlook MEM Trials Schedule EWR Trials DCL Parcipitants
E N D
Data Communications Program MEM/EWR ATCT DCL Trials Status Updates To: DCIT21 Plenary From: Matt Maki Date: 02.01.2013
Agenda • MEM Trials Operational Status • DTAP Build 6 and Phase 2 Outlook • MEM Trials Schedule • EWR Trials DCL Parcipitants • EWR Trials Activities and Schedule Status
MEM Trials Operational Status • MEM Limited Trials Underway: • Initial Revenue DCL Op CAF successfully issued on Jan 17, FDX303 KMEM-KMIA P2125z • Second Revenue DCL Op CAF and Revised UM80 successfully issued on Jan 29, FDX303 KMEM-KMIA P2125z • DTAP Build 4.5 software version utilized • Additional required DTAP software Build 6 modifications discovered during an attempted DCL Test Op on 1/22 (FDX9056 KMEM-KMEM) • Multiple AFN login/logout before initial DCL approved results in processing errors • 4 PTRs written against issues • Limited Trials planned for daytime, domestic operations (MD-11): • Additional B777 CAF DCL Ops being considered by FAA-FDX • Limited Trials scheduled to run until March 8 (Fri)
1/29 FDX303 KMEM-KMIA P2125z Initial DCL – Cleared As Filed (CAF) KMEM.PIEPE1.PIEPE.IBUFY.MGM.J20.SZW.SSCOT1.KMIA
1/29 FDX303 KMEM-KMIA P2125z Revised DCL – Full Route Clearance UM80 KMEM.BBKNG1.BBKNG.KERMI.VUZ.SZW.SSCOT1.KMIA • Pre-Taxi Revision Issued • Revised UM79 Not Eligible Due to SZW SSCOT1 Transition Common Re-Join Point
1/29 FDX303 AOC Dispatch Messages QU NQAASFX .MEMCLYA 292056 _CCI 001DCL COURTESY COPY - NOT AN ATC CLEARANCE FDX303 KMEM H/MD11/Q P2125 153 370 CLEARED TO KMIA AIRPORT PIEPE1.PIEPE THEN AS FILED MAINT 05000FT FREQ 124.650 ================================================== QU NQAASFX .MEMCLYA 292101 _CCR 002DCL COURTESY COPY - NOT AN ATC CLEARANCE FDX303 KMEM H/MD11/Q P2125 153 370 REVISED RTE BBKNG KERMI VUZ3340N08653W SZW3033N08422W BBKNG1.BBKNG MAINT 05000FT REVISED FREQ 124.150
DTAP Build 6 and P2 Outlook • Build 6 delivery to FAA on Feb. 27: • SE2020 ATP issued to commence work • Final baseline FAA requirements provided to Thales • Includes updated PTRs resulting from Build 4.5 Trials Ops results • FAA currently reviewing Test Plan Book in advance of scheduled FAT testing at Thales on Feb 20-21 • Build 6 will be deployed at MEM and EWR Trials sites to start Full Functionality 24x7 Trials Ops • Scheduled MEM 24x7 Full Trials start estimated for April 30 • DTAP P2 requirements identified and being drafted: • Includes EWR specific requirements resulting from OT • Scope/Cost to be provided by Thales • Proposed summer P2 delivery to FAA
DCIT Plenary Slide – MEM Schedule • The Milestone Schedule Outlook: • Build 6 WJHTC Installation: February 27 • Build 6 WJHTC Functional Testing: March 4-15 • MEM Limited Full Functionality Trials: March 26 – April 26 • MEM Full FANS Fleet 24x7 Trials Start: April 30 • Limited Full Functionality Trials proposed for March 26: • Additional FAT scope and FDX schedule availability moves schedule to the right • Goal is 50 flight DCL operation shakeout • Minimum 35, 20 MD-11, 15 B-777 • Milestone checkpoint approvals planned
EWR Trials DCL Participants • Currently 4-6 daily ad-hoc UAL EWR FANS DCL commitments in hand from April thru summer • UAL action pending to identify potential maximum manual FRC DCL Flight Plan filings • Additional FANS carrier/operations @ EWR being researched • FDX & UPS already stated intent to operate • Subsequent DCIT and NY Port Authority Delay Initiative Meeting Groups • Trials Site #2 goal is to maximize # of DCL operations across multiple operators • FAA Cost/Benefit calculations
EWR Trials Schedule/Activities • Trials start projected for April 22: • Schedule development still on-going • MEM 120 day summit and parallel MEM start dates issues open • Ahead of May-Sept Freeze Out @ EWR • ATC training complete by Trials start • Limited Trials Ops during summer and internal ATC hands on Ops slow roll • Trials start with B6 • IMP On-Going Activities: • Site Survey complete – Harris Site Implementation Plan Complete • Feb 13 @ EWR ATCT Implementation Review and commence TDLS Console work • FTI Telco ordered – March 15 Cutover • ISSM Authorizations in place • Space, HADDS, FDIO Test NCPs in progress • DTAP4 HW procurement request submitted
Questions ? KMEM