An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SYS 798/OR 680 1 INVESTMENT STRATEGY Schedule Using Program Evaluation and Review Technique PERT

  2. PERT : General Review 2 • Advantages – • Helps determine where greatest effort should be made to keep project on schedule • Ability to evaluate effects of change on program • Allows large amounts of data to be represented in a well organized diagram • Disadvantages – • Complexity • Expensive to maintain and utilize

  3. PERT Terminology 3 Event: Equivalent to a milestone indicating when an activity starts or finishes. Activity: The element of work that must be completed Critical Path: Longest path through the network and determines the duration of the project. Slack Time: Difference between the latest allowable date and earliest expected date.

  4. PERT Questions 4 • Questions that need to be answered before converting projects into PERT charts: • What job immediately precedes this job? • What job immediately follows this job? • What jobs can be run concurrently?

  5. Total Pert/CPM Planning- 6 Steps 3 List Activities Arrange Activities Review Activities Identify Activities Times Identify Critical Path Add Dates

  6. Total PERT Step 1 – List Activities 4 List Activities Arrange Activities Review Activities Identify Activities Times Identify Critical Path Add Dates • Investment Strategy Milestones • Team Formed • Project Proposal Approved • Activities Schedules determined • Requirements Release • Data and Documentation Gathered • Design Completed • Program and Coding • Simulations • Analysis • Final Report • Final Presentation • Step 1 – List Activities from Events • Project Team Organization • Project Proposal • Project Approval • Development Activities Schedule • Requirements Elicitation • Researches and Documentation • Modeling • Data Gathering • Programming and Coding • Simulations • Results Analysis • Report Preparation • Presentation Preparation • Alternatives Solutions • Presentation Rehearsal • Polish Report and Presentation • Final Presentation

  7. Total PERT Step 2 - Arrange Activities 5 List Activities Arrange Activities Review Activities Identify Activities Times Identify Critical Path Add Dates

  8. Total PERT Step 2 -Arrange Activities (Cont’d) 6 List Activities Arrange Activities Review Activities Identify Activities Times Identify Critical Path Add Dates

  9. Total PERT Step 2: Arrange Activities (cont’d) 7 List Activities Arrange Activities Review Activities Identify Activities Times Identify Critical Path Add Dates 13 4 8 1 2 3 5 10 11 12 16 17 6 7 9 14 15 Legend Event Activity

  10. Total PERT Step 3: Activities Review 8 List Activities Arrange Activities Review Activities Identify Activities Times Identify Critical Path Add Dates • Have all activities been identified? • Should any be removed? • Should any be added? • Are the interrelationships correct?

  11. Total PERT Step 4 –Identify Activities Time 9 List Activities Arrange Activities Review Activities Identify Activities Times Identify Critical Path Add Dates

  12. Total PERT Step 4: Identify Activities Time (Cont’d) 10 List Activities Arrange Activities Review Activities Identify Activities Times Identify Critical Path Add Dates

  13. Total PERT Step 4: Identify Activities Time (cont’d) 11 List Activities Arrange Activities Review Activities Identify Activities Times Identify Critical Path Add Dates 7 13 4 8 24 5 1 5 7 1 14 8 1 5 5 1 2 3 5 10 11 12 16 17 10 5 5 15 1 1 10 4 24 6 7 9 14 15 Legend Event Activity 10 Time

  14. Total PERT Step 5: Critical Path 12 List Activities Arrange Activities Review Activities Identify Activities Times Identify Critical Path Add Dates 7 13 4 8 24 5 1 5 7 1 14 8 1 5 5 1 2 3 5 10 11 12 16 17 10 5 5 15 1 1 10 4 24 6 7 9 14 15 Legend Event Activity 10 Time (days) 2

  15. Total PERT Step 6: Add Dates 15 List Activities Arrange Activities Review Activities Identify Activities Times Identify Critical Path Add Dates 7 13 August 31, 2009 4 December 18, 2009 8 24 5 1 5 7 1 14 8 1 5 5 1 2 3 5 10 11 12 16 17 10 5 5 15 1 1 10 4 24 6 7 9 14 15 Legend Event Activity 10 Time (days) 2