GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S 4.1.7

Gamma-ray Large Area Space Telescope. GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S 4.1.7 Aug-1 Monthly Review Gunther Haller haller@slac.stanford.edu (650) 926-4257. TEM/TPS Status. Status All units delivered by assembly vendor. Contract being closed.

kreid
Download Presentation

GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S 4.1.7

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S 4.1.7 Aug-1 Monthly Review Gunther Haller haller@slac.stanford.edu (650) 926-4257

  2. TEM/TPS Status • Status • All units delivered by assembly vendor. Contract being closed. • Qual unit review still to occur • 14 flight units delivered to I&T • A & B & 12 more units • 6 units ready to be reviewed (i.e. finished/passed all testing) • 2 of those units were demated and will be used to replace TwrA and TwrB TPS’s • Last unit in TV until next Sunday • To do • Review of end data packages for 4 units above • Review of last unit presently in TV • Modification of 2 TPS’s taken off TwrA and B • Mating with TEM’s • Vibration • End data package review

  3. PDU Status and Schedule • 1st unit (flight) • All testing complete • To do: • Closing of NCR’s • Collecting/posting data • Review • 2nd unit (spare) • Pre-coat stage box just received at SLAC • Testing (safe-to-mate & performance) to start next week • Followed by • Return to vendor for conformal coating • Environmental testing • Schedule depends on setting priorities compared to other modules (e.g. SIU). Assume low priority compared to all others for now.

  4. GASU Status and Schedule • First Unit • In conformal coating at vendor, followed by integration with flight harness • From last months review: • Estimated Delivery of final box at SLAC: Sept 15 • Best estimate is now Sept 21 due to parallel work on SIB, etc • Followed by test/mass/TC/test/vib/test/TV: 23 days • Followed by EMI (10 days) • Estimated delivery to I&T: first week of November • Schedule for 2nd unit • Estimated delivery to I&T: 6 weeks after delivery of first unit

  5. SIU/EPU (1) • SLAC Qual testing of boards assembled at Aeroflex • Testing was all completed without failures • To do: correlate pins tested to results of X-rays from GSFC, await file from GSFC • Backplanes • Assembled cCPI connectors on flight backplanes at SAI • SAI assembled 7 backplanes (3 to follow) • I had short, neither SLAC nor SAI could repair. However pins are not used so NCR with “use-as-is” • 7 boards were xrayed, some pins were touched-up, re-xrayed • 3 board were mailed to Aeroflex for remaining assembly • Are in conformal coating followed by harness assembly • Additional ones will be mailed to Aeroflex after balance of 3 backplanes from SAI are received and evaluated and compared to other 4 backplanes. • Hope to receive at least 1 fully assembled backplane end of next week (for proto-flight testing of SIU)

  6. SIU/EPU (2) • 1st SIB, LCB, CPS (for proto-flight testing of SIU) • One each was tested, pre-conformal stage • (also xray’s were taken and some pins were touched up, the connectors had been assembled at AF before SAI experiments started) • Integrated in SIU crate with RAD750 processor • Short performance tests at –40C and 55C passed • Boards were sent back to Aeroflex for conformal coating • Final SIB and LCB assemblies were received at SLAC yesterday • CPS expected beginning of next week • Note that this SIB contains chlorine-contaminated EEPROM, other modules could be flight • 2nd and 3rd SIB/LCB/CPS (for 1st and 2nd flight SIU/EPU) • cCPI connectors were assembled at SAI • Xrayed and touched-up at SLAC • Sent to AF for further assembly • Pre-conformal coat boards expected next week for testing at SLAC • Followed by conformal coating • Integration in 1st and 2nd SIU (or EPU) • Environmental testing • Expected delivery to I&T 11/30 –12/5 • Remainder of crates follow in 5-day increments (mainly TV) • cCPI connectors were just assembled by AF on boards • Manual assembly will follow • EEPROM for SIB: • Passed CSI at Austin Semi • Delivery to SLAC is Sept 15

  7. Harness & Heater Control Box & Interconnect Box • Harness in assembly, almost complete (some spare cables in rework) • HCB • Boards assembled • Await harnesses and enclosures • Assembly lower priority compared to GASU/SIU • HIB (Interconnect box) • Parts kitted at SLAC • To be assembled at SLAC

  8. Thermo-testing support/ VSC • EGSE for thermal-test shipped to Lockheed • TV Testing to be completed end of this week • VSC’s available for FSW/I&T • Remaining features of VSC being implemented

  9. Level 3 Milestone Count

  10. Level 3 Milestone List

  11. Level 3 Milestone List

  12. Level 3 Milestone List

  13. Level 3 Milestone List

  14. Cost Report

  15. FTE Report (DOE/NASA-funded only)