An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Excelsior Energy’sMesaba Energy Project Update for the NM-SPG August 16, 2006

  2. Current Project Parameters • Two 606MW IGCC units • ISDs 2011 and 2013 • Primary Site- West Range • POI---Blackberry 230kV Sub • Near Taconite, MN in Itasca County • Alternate Site- East Range • POI---Forbes 230kV Sub • Near Hoyt Lake, MN in St. Louis County • Designated as an Innovative Energy Project under special MN Legislation

  3. MISO LGIP Current Status

  4. Transmission Progress to Date • Transmission Concept Screening Study July 2003 • East Range GO Analysis August 2004 • East Range GI Request to MISO October 2004 • Queue # 38280-01, Project G477 • First Unit 531/552MW ISD 2010 • Network Resource Service • G477 Feasibility Study Report March 2005 • 6 months • West Range GO Analysis May 2005 • West Range GI Request May 2005 • Queue # 38491-01, Project G519 • First Unit 600MW ISD 2010 • Network Resource Service

  5. Transmission Progress to Date • G519 ‘Out of Queue’ Study Agreement August 2005 • West & East Range Preliminary GO Facilities Engineering Designs December 2005 • West & East Range GO Analyses Updates December 2005 • G519 Feasibility Study Results December 2005 • 8 months • G477 & 519 System Impact Study Results April 2006 • 11 and 19 months • G477 & 519 restudy of short circuit results July 2006 • Second unit GI request submitted January 2006 • Designated G597

  6. Transmission Progress to Date • G597 Feasibility Study Report July 2006 • G477&519 Facilities Studies underway July 2006 • MP has contracted to perform • G597 SIS Agreement Executed August 2006 Note: Between July 2004 and December 2005 Excelsior performed six series of powerflow studies to evaluate GO facilities and network reinforcements

  7. MISO Study Results • Project G477 SIS (Forbes POI) • Powerflow : No problems identified • Short Circuit : Several pre-existing over-dutied breakers but no new ones caused by G477 • Stability : All simulations are stable and within damping criteria. No transient low voltage violations. • Deliverability Analysis: Failed • Awaiting MISO study proposal to continue NRIS process • TSR submitted by Xcel for NITS (local capacity resource)

  8. MISO Study Results • Project G519 SIS (Blackberry POI) • Powerflow : Some issues identified during contingencies. Resolved with the addition of a new Boswell-Riverton 230kV line. • Short Circuit : Several pre-existing over-dutied breakers delete [plus four new 115kV breakers at Nashwauk Sub due to G519] • Stability : All simulations are stable and within damping criteria. No transient low voltage violations. • New Boswell-Riverton 230kV line was included in these studies. • Deliverability Analysis: Failed • Awaiting MISO study proposal to continue NRIS process • TSR submitted by Xcel for NITS (local capacity resource

  9. MISO Study Results • Project G597 Feasibilty Study (Blackberry POI) • Powerflow: numerous local contingency violations identified • Not unexpected with both MEP II and new 800MW NE MN unit included without any network upgrades • Short Circuit: four Nashwauk 115kV breakers overdutied Note: Modeling didn’t include proposed Minnesota Steel Plant or CAPX 2020 Projects

  10. Other Mesaba Energy Project Progress • Filing made 12/23/05 with MPUC for a PPA with Xcel Energy • under Innovative Energy Project Legislation • Joint Siting/Routing Application made 6/16/06 for both units, all GO facilities, and gas pipeline. • Application accepted as complete 7/6/06.

  11. Proposed GO Facilities • G519: 9 mile double circuit 345kV steel pole structures, operated 230kV for MEP I • G477: Two 345/115kV steel pole lines replacing existing 115kV structures for most of their 34 and 37 mile routings, with 345kV side operated 230kV for MEP I

  12. West Range GO Facilities

  13. West Range GO Routings

  14. East Range GO Facilities

  15. East Range GO Routings

  16. Questions??