1 / 26

ALCON LABS

ALCON LABS. Project Chiron SMU TEAM ALCON. Project Overview. Project Background Problem Description & Core Objectives Action and Approach Plan Analysis of Situational Approach Analysis and Managerial Interpretation Recommendations. Project Background.

kura
Download Presentation

ALCON LABS

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ALCON LABS Project Chiron SMU TEAM ALCON

  2. Project Overview • Project Background • Problem Description & Core Objectives • Action and Approach Plan • Analysis of Situational Approach • Analysis and Managerial Interpretation • Recommendations

  3. Project Background • October 2003: Alcon Madrid manufacturing plant closed down • Madrid’s product baseline of 170 SKUs and 12 million units were transferred to Fort Worth headquarters • Before the Madrid divesture, the Fort Worth manufacturing plant was producing 230 to 250 SKUs and 70+million units

  4. Definition of the Problem • Whitestock Lines 1 & 2 • Production inefficiency and delays • Lagging downtime • Line clearances (LC) occupy 20-30 minutes • LC occurs 4-5 per day • Loss of Capacity

  5. Core Objectives Primary objectives: • Minimizing splits • line clearances and/or QA • Maximizing utilization of fill rooms Secondary objective: • Optimizing the facility layout • Optimizing the lot size (batch) or economic order quantity levels

  6. Core Objectives - Benefits • Significant cost savings • Improved uptime and process efficiency • Improved capacity levels • Improved overall throughput speed and other technical performance measures • Reduced or eliminated inventory levels and other unnecessary costs • Minimized idleness of employees (i.e. employee output efficiency)

  7. Action & Approach Plan • Short-term perspective • Determine and measure Alcon Labs Manufacturing processes to locate source of problem associated with LC • PAT and SMED method • Long-term perspective • Converting 2-step process to inline process • ProModel: Simulation Models

  8. Analysis of Situational Approach Short-term approach • Whitestock Line 1 & 2: • Observed and measured the “splits” process steps for cycle time improvements • Recorded the sequence of repeatable activities with measurable inputs, value-added activities, and measurable outputs

  9. Analysis of Situational Approach Short-term approach • PAT Method • SMED Method • Internal and External Setup activities • Improve cycle time or changeover/roll-over time by reorganizing and reducing setup activities as well as resources and inventory waste and rescheduling production schedules for low quantity batches while sustaining high product quality • Other benefits of setup reduction include lower cost (less inventory), better flexibility, better worker utilization, shorter lead time, increased capacity, and most importantly, less process variability

  10. Analysis of Situational Approach • SMED Method: Process Flow chart

  11. Analysis of Situational Approach • SMED Method: BENEFITS

  12. Analysis of Situational Approach Long-term approach • Converting 2-step process to inline process • Observation & Data Collection - process and layout, - setup/changeover times, - speeds and capacity, etc. - ProModel Simulation software • Assumptions • Current Process Simulation Model • New Process Simulation Model

  13. Analysis of Situational Approach Long-term approach • Variables/Functions - locations - entities - network paths - process/logic - arrivals • product differentiation • setup downtimes

  14. Analysis of Situational Approach Long-term approach: Assumptions • Setup times for each machine were calculated using an average from the statistics provided. • Simulation models are programmed to run at particular speed as opposed to individual actual speeds. • Offline filling and storage time and activities are not accounted for in the simulation model. • The proposed filler speeds and product specifics are assumed to be similar to the current equipment capabilities • When locations and resources appear to be idle, setup downtimes are in occurrence.

  15. Analysis & Managerial Interpretation Short-term Approach Alcon Operation or Process steps • Staging (storage) area • Line area: inspection • Changeover • Production • Finished goods area • Reconciliation with Materials Office

  16. Analysis & Managerial Interpretation Short-term Approach • Changeover is the main cause for low efficiency. • Steps in setup process • Preparation, after-process adjustments, checking of materials and tools • Mounting and removing blades, tools, parts • Measurements, settings, and calibrations • Trial runs and adjustments

  17. Analysis & Managerial Interpretation Short-term Approach • Calibration and Trial Runs occupy a total of 85% of total time (changeover and LC time)!

  18. Analysis & Managerial Interpretation Short-term Approach: • Changeover setup adjustments • Labelers • Cartoners • Magazines • Ink Jet Coder • Wrapper/Packaging • Adjustments are made by trial-and-error as well as intuition

  19. Analysis & Managerial Interpretation • Short-term Approach: Changeover

  20. Analysis & Managerial Interpretation Short-term Approach: • Other inefficiencies: • Incorrect Madrid Translations • Disconnected communication across divisions

  21. Analysis & Managerial Interpretation Long-term Approach: • Decreased product handling and movement • Increased flexibility and capabilities • Increased utilization, productivity levels, and capacity • Automated flex pack line • Decreased downtimes

  22. Recommendations Long-Term Solution • Recommend 1-year further analysis and research - costs - equipment - feasibility requirements - build a more accurate model - implementation

  23. Recommendations Short-Term Solution • Strongly recommend forming a changeover team of 4-5 members • Labelers • Cartoners • Magazines • Ink Jet Coder • Wrapper/Packaging • Update changeover team regarding production schedules for advanced preparation

  24. Recommendations Short-Term Solution • Allocate secondary space for storage • Color code • Next Raw materials – red (stop) • Current Raw Materials and Finished product – green (go)

  25. Recommendations Short-Term Solution • Streamline line clearance to a parallel process • Cross-train personnel • Require employees to perform other functions in the changeover process • Ensure prompt arrival of Bill of Materials • If items aren’t available, contingency plan should be developed • Improve coordination between Marketing, Planning, and Production divisions • Function standardization • Replace bolts with one-time tighteners! • Mark individual calibration settings for each product on each line for easy adjustments

  26. Questions? • SMU TEAM ALCON • Benjamin Luong • Chris Davis • Cuong Ngo • Cindy Nguyen • Shanta Ramdhanny

More Related