260 likes | 461 Views
ALCON LABS. Project Chiron SMU TEAM ALCON. Project Overview. Project Background Problem Description & Core Objectives Action and Approach Plan Analysis of Situational Approach Analysis and Managerial Interpretation Recommendations. Project Background.
E N D
ALCON LABS Project Chiron SMU TEAM ALCON
Project Overview • Project Background • Problem Description & Core Objectives • Action and Approach Plan • Analysis of Situational Approach • Analysis and Managerial Interpretation • Recommendations
Project Background • October 2003: Alcon Madrid manufacturing plant closed down • Madrid’s product baseline of 170 SKUs and 12 million units were transferred to Fort Worth headquarters • Before the Madrid divesture, the Fort Worth manufacturing plant was producing 230 to 250 SKUs and 70+million units
Definition of the Problem • Whitestock Lines 1 & 2 • Production inefficiency and delays • Lagging downtime • Line clearances (LC) occupy 20-30 minutes • LC occurs 4-5 per day • Loss of Capacity
Core Objectives Primary objectives: • Minimizing splits • line clearances and/or QA • Maximizing utilization of fill rooms Secondary objective: • Optimizing the facility layout • Optimizing the lot size (batch) or economic order quantity levels
Core Objectives - Benefits • Significant cost savings • Improved uptime and process efficiency • Improved capacity levels • Improved overall throughput speed and other technical performance measures • Reduced or eliminated inventory levels and other unnecessary costs • Minimized idleness of employees (i.e. employee output efficiency)
Action & Approach Plan • Short-term perspective • Determine and measure Alcon Labs Manufacturing processes to locate source of problem associated with LC • PAT and SMED method • Long-term perspective • Converting 2-step process to inline process • ProModel: Simulation Models
Analysis of Situational Approach Short-term approach • Whitestock Line 1 & 2: • Observed and measured the “splits” process steps for cycle time improvements • Recorded the sequence of repeatable activities with measurable inputs, value-added activities, and measurable outputs
Analysis of Situational Approach Short-term approach • PAT Method • SMED Method • Internal and External Setup activities • Improve cycle time or changeover/roll-over time by reorganizing and reducing setup activities as well as resources and inventory waste and rescheduling production schedules for low quantity batches while sustaining high product quality • Other benefits of setup reduction include lower cost (less inventory), better flexibility, better worker utilization, shorter lead time, increased capacity, and most importantly, less process variability
Analysis of Situational Approach • SMED Method: Process Flow chart
Analysis of Situational Approach • SMED Method: BENEFITS
Analysis of Situational Approach Long-term approach • Converting 2-step process to inline process • Observation & Data Collection - process and layout, - setup/changeover times, - speeds and capacity, etc. - ProModel Simulation software • Assumptions • Current Process Simulation Model • New Process Simulation Model
Analysis of Situational Approach Long-term approach • Variables/Functions - locations - entities - network paths - process/logic - arrivals • product differentiation • setup downtimes
Analysis of Situational Approach Long-term approach: Assumptions • Setup times for each machine were calculated using an average from the statistics provided. • Simulation models are programmed to run at particular speed as opposed to individual actual speeds. • Offline filling and storage time and activities are not accounted for in the simulation model. • The proposed filler speeds and product specifics are assumed to be similar to the current equipment capabilities • When locations and resources appear to be idle, setup downtimes are in occurrence.
Analysis & Managerial Interpretation Short-term Approach Alcon Operation or Process steps • Staging (storage) area • Line area: inspection • Changeover • Production • Finished goods area • Reconciliation with Materials Office
Analysis & Managerial Interpretation Short-term Approach • Changeover is the main cause for low efficiency. • Steps in setup process • Preparation, after-process adjustments, checking of materials and tools • Mounting and removing blades, tools, parts • Measurements, settings, and calibrations • Trial runs and adjustments
Analysis & Managerial Interpretation Short-term Approach • Calibration and Trial Runs occupy a total of 85% of total time (changeover and LC time)!
Analysis & Managerial Interpretation Short-term Approach: • Changeover setup adjustments • Labelers • Cartoners • Magazines • Ink Jet Coder • Wrapper/Packaging • Adjustments are made by trial-and-error as well as intuition
Analysis & Managerial Interpretation • Short-term Approach: Changeover
Analysis & Managerial Interpretation Short-term Approach: • Other inefficiencies: • Incorrect Madrid Translations • Disconnected communication across divisions
Analysis & Managerial Interpretation Long-term Approach: • Decreased product handling and movement • Increased flexibility and capabilities • Increased utilization, productivity levels, and capacity • Automated flex pack line • Decreased downtimes
Recommendations Long-Term Solution • Recommend 1-year further analysis and research - costs - equipment - feasibility requirements - build a more accurate model - implementation
Recommendations Short-Term Solution • Strongly recommend forming a changeover team of 4-5 members • Labelers • Cartoners • Magazines • Ink Jet Coder • Wrapper/Packaging • Update changeover team regarding production schedules for advanced preparation
Recommendations Short-Term Solution • Allocate secondary space for storage • Color code • Next Raw materials – red (stop) • Current Raw Materials and Finished product – green (go)
Recommendations Short-Term Solution • Streamline line clearance to a parallel process • Cross-train personnel • Require employees to perform other functions in the changeover process • Ensure prompt arrival of Bill of Materials • If items aren’t available, contingency plan should be developed • Improve coordination between Marketing, Planning, and Production divisions • Function standardization • Replace bolts with one-time tighteners! • Mark individual calibration settings for each product on each line for easy adjustments
Questions? • SMU TEAM ALCON • Benjamin Luong • Chris Davis • Cuong Ngo • Cindy Nguyen • Shanta Ramdhanny