Excavating and Lifting

Excavating and Lifting. Hmwk Ch 2 # 1,2,5,8 Ch 3 #2,4,6,10. Excavators & Crane Shovels. Crane Shovel – cable operated machines Shovel Backhoe Dragline Clamshell Mobile crane Pile driver. Excavators & Crane Shovels. Hydraulic Excavators Faster cycle time than shovels

Download Presentation

Excavating and Lifting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Excavating and Lifting Hmwk Ch 2 # 1,2,5,8 Ch 3 #2,4,6,10

  2. Excavators & Crane Shovels • Crane Shovel – cable operated machines • Shovel • Backhoe • Dragline • Clamshell • Mobile crane • Pile driver

  3. Excavators & Crane Shovels • Hydraulic Excavators • Faster cycle time than shovels • Higher bucket penetrating force • More precise digging • Easier operator control • Attachments – pg 41 - 43

  4. Excavators & Crane Shovels • Parts – Figure 3-2 • Carrier or mounting • Track • Excellent on-site mobility – will go anywhere • Low ground pressure – good for low trafficablity soils • truck & wheel mountings • Greater mobility between job sites – faster • Require better surfaces to work on • Revolving superstructure containing power and control units • Front end assembly

  5. Production • Need to know volume of material in one bucket load Figure 3-1 • Plate line capacity – volume contained in outline of bucket • Struck capacity – volume when mat’l is struck off even w/ sides of bucket • Water line capacity – assumes material only to lowest edge of bucket • Heaped capacity – max volume that can be placed in bucket without spillage

  6. Production • Ratings usually based on struck volume • Assumption is made that since bucket is usually heaped that a 5 cy bucket will pick up 5 cy of bank not loose • Better to use bucket fill factors – Table 3-2

  7. Operation & Employment • Excavators • Fig 3-3 & 3-4 • Trenching work • Production estimating • Production (LCY/hr) = CxSxVxBxE • C – cycles/hr • S – swing depth factor T 3-4 • V – heaped bucket volume • B – bucket fill factor • E – job efficiency • Trenching work may also require a fall in factor for dirt going back in the trench T 3-5

  8. Shovels • Larger than excavators • Good for excavating above track line • Digs using • Breakout force and crowding force • Can form its own roadway • Can shape sides of cut and dress slopes • Should have a vertical face to dig against • Production is found same way

  9. Trenching Technology • Good for digging a narrow trench with the spoil going to the side of the trench • Chain trenchers, ladder trenchers, bucket wheel trenchers

  10. Trenchless Tech • Pipe jacking • Thrust boring • Pipe bursting

  11. Cranes • Lifting, lowering transporting loads over 3D • Components Fig 3-22 • Load chart F 3-24 • Heavy Lift cranes • F 3-25 – 26 • Tower Cranes • F 3-27 - 29