1 / 9

Gillentown Trailhead Access Control Project

Gillentown Trailhead Access Control Project. Images are before the Yamaha Grant. Grant was provided to the SSRT for Access Control. Contractors Discussing Project. Brooks Welding and C.E. Concrete December 2012 Met to discuss Project . Breaking Ground January 8, 2013.

kylia
Download Presentation

Gillentown Trailhead Access Control Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Gillentown Trailhead Access Control Project • Images are before the Yamaha Grant • Grant was provided to the SSRT for Access Control

  2. Contractors Discussing Project Brooks Welding and C.E. Concrete December 2012 Met to discuss Project

  3. Breaking Ground January 8, 2013 Funded partially by Yamaha and Snow Shoe Rails to Trails.

  4. Concrete Bollards Installed

  5. Fence Post Installation by R&R Fencing Started Jaunary 23, 2013

  6. Installation of Rail Fencing by Brooks Welding Family Owned and Operated company Brooks Welding installation of the railing was flawless. Installation Date: 03-19-2013

  7. Continuation of Rail and Gate Installation Installation Completed 5-2-2013

  8. Painting of Fence Painting provided by community service volunteers Special Thanks Centre County Probation Office

  9. Project Completed 05-29-2013

More Related