1 / 4

15B Critical path analysis

15B Critical path analysis. In a critical path analysis, edges represent activities. Nodes (vertices) represent the end of one activity and the start of subsequent activities. The immediate predecessor of an activity is an activity that must be completed before the next activity can commence.

kynan
Download Presentation

15B Critical path analysis

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 15B Critical path analysis

  2. In a critical path analysis, edges represent activities. • Nodes (vertices) represent the end of one activity and the start of subsequent activities. • The immediate predecessor of an activity is an activity that must be completed before the next activity can commence.

  3. The earliest start time (EST) is the earliest that any activity can be started after all prior activities have been completed and is recorded in the triangle preceding the activity. • Float time is the difference in time between those activities that cannot be delayed and those that can. • The latest start time is the latest time that an activity may begin without delaying the entire project.

  4. The critical path is the path through the network along activities that cannot be delayed without delaying the entire project. • Ex 15B, Q. 5, 6, 7, 8, 9, 10, 11b, 11d, 12

More Related