Test Dates 1. Present request to ESTEC (just after last TIM):Test stand arrives week of 9 Jan. 09AMS arrival and setup start 16 Jan.LSS activities 30 Jan.
E N D
1. Test Plan at ESTECAMS TIM, CERNApril 18, 2008 Joseph Burger – MIT – General
Marco Molina – CGS – TV/TB Test Spec.
Tim Urban – JSE – EMI Test Spec.
2. Test Dates 1 Present request to ESTEC (just after last TIM):
Test stand arrives week of 9 Jan. 09
AMS arrival and setup start 16 Jan.
LSS activities 30 Jan. – 20 Mar.
EMI test start 27 Mar.
Pack up and leave 3-14 Apr.
At that time, the Aeolus experiment was supposed to arrive for the LSS in late March – early April
3. Test Dates 2 This week’s schedule discussions have us ready to go to ESTEC later - 25 Jan., and leaving in mid May 2009
Gaetan Piret says the Aeolus experiment, which follows us in the LSS, is now expected to arrive later than April 2008. There is a scheduling meeting today, and he will report to us afterwards
We should request a new time slot consistent with our schedule
4. Teleconference with ESTECThursday, 17 April TVT test specification and drawings on stand and emplacement given to ESTEC this week
G. Piret will comment by Tuesday, and we will have another teleconference Thursday afternoon, next week
G. Piret will get weekly updates of ESTEC related action items from integration teleconferences, and we will discuss them with him regularly