1 / 22

OVERVIEW OF INDIAN POWER SECTOR AND PLAN FOR 12 th / 13 th PLAN

OVERVIEW OF INDIAN POWER SECTOR AND PLAN FOR 12 th / 13 th PLAN. Installed Capacity (as on 30.09.2010). Total Capacity as on 30.09.2010= 1,64,835 MW. Installed Capacity (MW) as on 30-09-2010 (Type-wise). Total Installed Capacity = 1,64, 835 MW.

kyrie
Download Presentation

OVERVIEW OF INDIAN POWER SECTOR AND PLAN FOR 12 th / 13 th PLAN

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. OVERVIEW OF INDIAN POWER SECTOR AND PLAN FOR 12th / 13th PLAN

  2. Installed Capacity (as on 30.09.2010) Total Capacity as on 30.09.2010= 1,64,835 MW

  3. Installed Capacity (MW) as on 30-09-2010 (Type-wise) Total Installed Capacity = 1,64, 835 MW

  4. Power Supply Position (Provisional) (April, 2010- September, 2010)

  5. Capacity addition during 11th Plan • Capacity addition target during 11th Plan: 78,700 MW • Capacity addition likely during 11th Plan as per MTA: 62,374 MW • Capacity commissioned during 11th Plan till 31.10.2010: 29,322 MW • Capacity under execution for likely benefits during 11th Plan: 33,436 MW • Capacity being attempted under Best Efforts: 12,590 MW

  6. Capacity addition likely during 11th Plan as per MTA

  7. Capacity commissioned during 11th Plan till 31.10.2010

  8. Capacity under execution for likely benefits during 11th Plan

  9. Growth of Transmission Sector (ckm) (as on 30.09.2010)

  10. CAPACITY ADDITION REQUIREMENT DURING 12th PLAN (2012-17)

  11. 17th EPS Demand - Summary of All India forecast

  12. Generation Capacity Addition 12th Plan: Basis • Demand - 17th EPS forecasts • Seasonal studies carried out to ensure optimum capacity addition would separately meet demand in each season also. • 11th Plan Capacity addition considered – 62,374 MW • Capacity retired - about 4,000 MW • Norms adopted – LOLP-0.2% and ENS- 0.05% • Spinning Reserve – about 11,000 MW (capacity corresponding to 5% Spinning Reserve) • Import – 1200 MW hydro from neighboring countries

  13. Generation Capacity Addition 12th Plan: Basis • Shelf of projects drawn up based on the status of projects (approx 1,30,000 MW). • Hydro and Nuclear projects accorded priority. • Generation Expansion Planning Models used to work out the capacity addition requirement to meet the projected demand.

  14. LOAD DURATION CURVE

  15. Capacity addition requirement during 12th Plan (fig in MW)

  16. Capacity under execution for likely benefits during 12th Plan

  17. CAPACITY ADDITION REQUIREMENT DURING 13thPLAN (2017-22)

  18. Capacity addition requirement during 13th Plan (fig in MW)

  19. Low Carbon Growth Strategy • Capacity Addition from Conventional fuel based plants complemented by Renewable Energy based plants to the maximum extent possible. • Highest priority to setting up of Hydro and Nuclear power plants. • Gas based plants to be accorded higher priority as compared to coal /lignite plants, to the extent feasible. • Efficiency improvement of existing stations, R&M of Old thermal power projects, and retirement of less efficient plants/old and small size generating units.

  20. Low Carbon Growth Strategy • Energy Conservation in generation and at consumer end. • Other measures to reduce pollution i.e. Reduction in T&D losses, Coal quality improvement. • Introduction of Clean Coal Technologies (Supercritical Technology, Ultra supercritical technology, IGCC etc). • Formation of Strong National Grid

  21. Thanks

More Related