RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.
Coordination with Railroad • Meet with Railroad Early in Project Development to Discuss • Railroad Track Operations are Very Important • Minimize Impact on RR Operations • LOA and RR Agreement
Superstructure Considerations • Safety • Highway Users • Railroad • Required Span for Horizontal Clearance • Column Protection • Adequate Vertical Clearance
Preferred Railroad Grade Separations 1. Overpass 2. UPRR Steel Deck Girder Standards • Deck Plate Girder w/ Steel Deck • Steel Girder w/ Conc Deck • Prestressed Beam w/ Conc Deck 6. Thru-Girder w/ Steel Deck
UPRR Deck Girder Standard • Depth-Top / Rail to Low Chord = 5’-5” • Steel Deck • 69 ft Max Span Length
Thru Girder • Depth-Top / Rail to Low Chord = 4’-6” • Steel Deck • 155 ft Max Span Length
Superstructure Considerations • TxDOT Design Requirements • UPRR-BNSF Design Guidelines • KCS Design Guidelines • Composite and Non-Composite Design • No Sacrificial Beams • Design for 30” Ballast • Ballast Depth for Concrete Tie
Vertical Clearance • Steel Deck Girder 16.5 ft • Steel Thru Girder-Bolt Bot Fl 17.5 ft • Prestressed Conc 17.5 ft • Hwy Over RR 23.33 ft
Railroad Underpass • 30% Submittal - Exhibit “A” • 60% Submittal • 90% Submittal • 100% PS&E Plans RR Agreement with Exhibit “B”
30% Submittal - Exhibit “A” • Preliminary: • Bridge Layout • Track Plan and Profile • Track Typical Sections • Structure Type Selection Report • Thru Girder • LOA Facilitate RR Review
Structure Type Selection Report • Required for Thru-Girder • Design Factors Considered • Underpassing Roadway Width • Clear Zone • Vertical Clearance • Consider All Options for Railroad
60% Submittal • Complete Bridge Plans • Complete Mainline and ShooFly Track Plans and Profiles • Railroad Track Standards • Mainline and ShooFly Typical Sections
60% Submittal, ctd • Track Sections every 50 ft • Division of Labor • Sequence of Work
90% Submittal • Revised Complete Bridge Plans • Revised Complete Mainline and ShooFly • Track Plans and Profiles • Mainline & ShooFly Typ Sections
90% Submittal, ctd • Track Sections every 50 ft • All Parts of PS&E that Affect the Railroad • All Specifications
100% Submittal • Complete PS&E That Affects RR • Complete Bridge Plans • Complete Mainline and ShooFly • Track Plans and Profiles • Mainline & ShooFly Typ Sections • Sequence and Division of Work • RR Agreement w/ Exhibit “B” Attachment
Track Plans & Sequence of Work • Bridge Replacement on Mainline • Longer Span and Increased Clearance • Track Raise • Shoo-Fly Construction Best Maintains RR Operations
Track Design Speed • Railroad Operating Dept Determines Speed • Mainline & ShooFly Same Speed ? • Existing Conditions • Future Upgrades • Design Speed Agreement
Railroad Track Grade Raise • No Grade Raise is Desirable • 6” Max Raise with Ballast Only • Use Subballast for Greater Raises • ShooFly Profile Grade • Ballast Delivery May Be an Issue
Bridge and Track Design Resources • TxDOT and Individual Railroad • Use TxDOT Annotated Guidelines • TxDOT Website • BRG Project Development Web Page • BRG FTP Site • AREMA and AASHTO
Bridge and Track Design Resources • UPRR, BNSF, KCS Guidelines and Standards • Updated Requirements and Standards TxDOT Bridge FTP Site: • ftp://bridge:txdot1@ftp.dot.state.tx.us • Railroad Bridge and Track Design
Ballasted Track Construction Specification • Bridge Division has a Reference Spec Available for Project Use • Bridge Division is Working to Develop Statewide Special Spec
Thank You
Estimated Railroad Costs 2008 Steel Deck Girder = $350 / SF with Steel Deck Steel Thru Girder = $450 / SF with Steel Deck Prestressed Beam = $225 / SF with Concrete Deck
Estimated Railroad Costs 2008 ShooFly Bridge with Open Deck = $350,000 / EA Temp Special Shoring = $60 / SF
Estimated Railroad Costs 2008 Ballasted Track = $240 / LF with 1 ft Raise Ballasted Track = $170 / LF No Raise Ballasted Track = $45 / LF Removal
Estimated Railroad Costs 2008 Turnout / Switch = $85,000 / EA Signal for Switch = $50,000 / EA Including Circuit
Estimated Railroad Costs 2008 Engineering Design Review = $100-175,000 And Construction Inspection Railroad Flagging = $900 / Day