Database Java Bean. Feng Chen. Outline. Tools and approaches Project overview Major contribution Project plan Cost estimate References Acknowledgment. Tools and Approach. Zaurak Oracle8i used to hold database Java, JDK1.3, Win-XP/win-NT used for development
E N D
Database Java Bean Feng Chen
Outline • Tools and approaches • Project overview • Major contribution • Project plan • Cost estimate • References • Acknowledgment
Tools and Approach • Zaurak Oracle8i used to hold database • Java, JDK1.3, Win-XP/win-NT used for development • JBuilder used as tool GUI, etc development
Overview Why Java Bean? -100% pure java programs. -simple to develop and easy to use. -enable well-formed objects to be manipulated in a builder tool during the design time
Overview Why Jbuilder?- “best of breed” in the rapid application development tool market. - fully support for building reusable components- visually design GUIs and rapidly build application.
Overview JavaApplication Database Connection bean Oracle8i List Database Items Bean Database Transaction bean
Contribution • The implementation of this project will have positive impacts on CIS 501 and CIS560 teachings and will help students to easily implement database java bean without having further knowledge of using advanced swing complements and latest JDBC technology.
Project Plan • Phase I: Specification Expected to finish by 9/15/2002 1. Topics selection and literature search. (8/30/2002) 2. Overview of project (9/5/2002) 3. Project plan (9/08/2002) 4. Cost estimation (9/10/2002) 5. Requirement (9/12/2002)
Project Plan • Phase II: Design Expected to finish by 10/20/20021. Design. (9/30/2002)2. Software quality assurance plan. (10/5/2002)3. Test plan: (10/10/2002) 4. Formal technical inspection.(10/15/2002)
Project Plan • Phase III: Implementation, Testing and Documentation: Expected to finish by 11/30/2002 1. Coding: (11/15/2002) 2. Testing: (11/20/2002) 3. Project Evaluation.(11/25/2002) 4. Documentation: (11/25/2002) 5. Prepare presentation III(11/30/2002)
Cost Estimates • The total loc for this project is around 2200 - 2800.
Simple Average Complex Sub-Total Count Weights Count Weights Count Weights Inputs 3 4 6 6 3 8 72 Outputs 3 4 0 6 0 7 12 Inquiries 0 4 3 6 0 7 18 Files 0 5 2 6 0 15 12 Interfaces 0 5 1 6 0 10 6 Total 120 Cost Estimates- Unadjusted function points
Cost Estimates- Adjusted function points (cont’) • Adjusted FP = FPunadjusted * (0.65 + 0.01 * (sum of ratings))= 120 * (0.65+0.01*41)= 127.2
Cost Estimate- COCOMO • KDSI = 2.8 KLOCPM = 2.4 * (KDSI) ^ 1.05 = 2.4 * 2.8^1.05 = 7.1 (person-month) TDEV = 2.5 * (PM) ^ 0.38 = 2.5 * 7.1 ^ 0.38 = 5.2 (month)
Reference [1]http://www.borland.com/[2] http://java.sun.com/products/javabeans/[3] L. Bernstein and A. Lubashevsky, "Living with Function Points", in Software Management, 5th Edition, 1997 [4] R. D. Stutzke, "Software Estimating Technology: A Survey", in Software Management, 5th Edition, 1997 [5] R. S. Pressman, "Software Engineering: A practitioner's approach", 4th Edition, 1997