ICS Integrated Corrections System

ICS Integrated Corrections System. State of Wisconsin Melanie Pederson ICS Business Change Manager Melanie.pederson@doc.state.wi.us May 1, 2006. Wisconsin DOC. Adult Institutions House 21,500 inmates 38 institutions and centers Community Corrections

lane-pope
Download Presentation

ICS Integrated Corrections System

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ICSIntegrated Corrections System State of Wisconsin Melanie Pederson ICS Business Change Manager Melanie.pederson@doc.state.wi.us May 1, 2006

  2. Wisconsin DOC • Adult Institutions • House 21,500 inmates • 38 institutions and centers • Community Corrections • Manage 71,000 adults and juveniles under community supervision • Probation, parole and extended supervision • Juvenile Corrections • House 570 youthful offenders • Three custodial facilities

  3. What is the ICS Project? • Replace five legacy offender information systems with one web-based application • Build a foundation for future DOC application development • Build a single source of decision support information across all three divisions • Complete four phases over four years • Support ASCA performance standards

  4. ICS Project Phases & Timeline • Phase 1a Institution Operations • May 2005 through April 2007 • Phase 2 Community Supervision • August 2006 through January 2008 • Phase 3 Offender Financials • June 2007 through October 2008 • Phase 4 Juvenile Corrections • March 2008 through July 2009

  5. Where We Are Now • Completed all of the JAD sessions for the 14 modules • Quality Assurance & DOC Workgroups testing customized software changes until June 2006 • Unit Acceptance Testing Aug – Sept 2006 • Pilot Testing Sept – Oct 2006 • Phased Implementation for Adult Institutions starts December 4, 2006 • Start planning for start of Phase 2

  6. Lessons Learned • Allow more time for the JAD sessions • Drive JAD session from the Business Process Documentation, not the software • Determine effective use of Quality Assurance • Expand and improve our communications and union involvement process • Provide clearer and stronger scope management • Create a common schedule at the project onset • Need for ‘smart’ flexibility