Concepts for Ultra Wideband Radio Systems (CUBS). Steering group kick-off meeting Tuesday, Jan. 27, 2004 9.15-11.00 CWC, TL246. Agenda. Opening Acceptance of the agenda Confirmation of the steering group and nomination of the steering group chair, vice chair and secretary
E N D
Concepts for Ultra Wideband Radio Systems(CUBS) Steering group kick-off meeting Tuesday, Jan. 27, 2004 9.15-11.00 CWC, TL246
Agenda • Opening • Acceptance of the agenda • Confirmation of the steering group and nomination of the steering group chair, vice chair and secretary • Project organization - responsible leader, project manager, project secretary - separate tsg, sponsors' tsg members • Overall and detailed research plan for 2004 • 2004 budget and financing • Consortium agreement • Project practices • FUBS simulator release • AoB • Next meeting • Closing CUBS Steering group Kick-off meeting, Jan 27, 2004
Nomination of the steering group, chair, vice chair and secretary • Proposal for SG members • Defence Forces: Heikki Rantanen (chair), Tuomo Reili • Elektrobit: Petteri Heino (vice chair), • Tommi Jämsä (deputy SG member) • Tekes: Kari Markus • CWC: Ian Oppermann, Jari Iinatti secretary: Matti Hämäläinen CUBS Steering group Kick-off meeting, Jan 27, 2004
Project organization Proposal • Responsible leader: prof. Jari Iinatti • Project manager: Lich.Tech. Matti Hämäläinen • Project secretary: M.Sc. Raffaello Tesi CUBS Steering group Kick-off meeting, Jan 27, 2004
Overall and detailed research plan for 2004 • CUBS extends the research started in FUBS with • old work packages • new work packages • application of interest: military sensor network • Planned to last three years (2004-2006) • Goal: demonstrate UWB sensor network operation at the end of 2006 • Currently, the funding is approved only for 2004 CUBS Steering group Kick-off meeting, Jan 27, 2004
During 2004, the preliminary research work for sensor network demonstration will be carried out by CWC • At 2005, a subcontractor will be involved to the project • hardware design and implementation • PJMicrowave is the most probable candidate to be a subcontractor due to the good co-operation in FUBS CUBS Steering group Kick-off meeting, Jan 27, 2004
Work packages • WP1: Multiband UWB system • In FUBS only single-band UWB concepts have been studied • IEEE802.15.3 promoted MB-UWB for high data rate applications • Performance with interference in AWGN and real channels • Models based on FUBS can be used • Schedule: months I-XII • Work amount: 15 mm • Output: journal paper, two conference papers CUBS Steering group Kick-off meeting, Jan 27, 2004
WP2: Single band UWB systems • the original UWB PHY approach • continues the work started in FUBS • simpler and more cost effective than MB-UWB • Schedule: months I-XII • Work amount: 13 mm • Output: journal paper, two conference papers, two M.Sc. Thesis (channel modeling) CUBS Steering group Kick-off meeting, Jan 27, 2004
WP3: UWB sensor networks • LPD/LPI capable military sensor network concept • low power consumption, low PSD • aiming for demonstrator at 2006 • T-MIL: Requirement specification for the future UWB sensor communication development to be carried out on 2005-2006. (2 mm) • T-LOC: Development of UWB based location algorithm for sensor network (7 mm) • T-POW: Power efficient communication protocols(8 mm) • Schedule: months I-XII • Work amount: 17 mm • Output: journal paper, two conference papers CUBS Steering group Kick-off meeting, Jan 27, 2004
WP4: Co-existence • using the second generation UWB transmitters • FCC capable • adjustable PRF and TX power • bipolar pulses, Tp is about 200 ps • Schedule: months I-XII • Work amount: 8 mm • Output: one journal paper, one conference paper CUBS Steering group Kick-off meeting, Jan 27, 2004
WP5: Capacity • single band and multi-band UWB • information theoretic approach • Schedule: months I-XII • Work amount: 6 mm • Output: 1 journal paper, 1 conference paper • Administration: 1 mm CUBS Steering group Kick-off meeting, Jan 27, 2004
Channel modelling • hospital • forest • supplementary path loss measurements • do we need? • own WP or to be included in existing WP? • man months need to be transferred from somewhere else CUBS Steering group Kick-off meeting, Jan 27, 2004
2004 budget and financing BUDGET Labour costs (60 mm) 145.678,00 € Side costs (68%) 93.234,00 € Total 238.912,00 € 238.912,00 € Overhead (75.1%) 179.422,00 € Equipments and software 5.000,00 € Travel costs 10.000,00 € TOTAL BUDGET 433.334,00 € CUBS Steering group Kick-off meeting, Jan 27, 2004
Financing for 2004 Tekes (60%) 260.000,00 € 260.000,00 € Industrial partners (40%) 173.334,00 € CWC (15,4%) 66.667,00 € Elektrobit (9,2%) 40.000,00 € Defence Forces (15,4%) 66.667,00 € TOTAL: 433.334,00 € 433.334,00 € CUBS Steering group Kick-off meeting, Jan 27, 2004
Consortium agreement • University has a new contract form for Tekes projects CUBS Steering group Kick-off meeting, Jan 27, 2004
Project practices • Do we separate the steering group and the technical group meetings? • Regularity • Secured directory for information dissemination • http://www.cwc.oulu.fi/cubs • login: cubs • password: • includes: • plans • documents • publications • admin documents • meeting slides, minutes • etc. CUBS Steering group Kick-off meeting, Jan 27, 2004
FUBS simulator • AoB • Next meeting CUBS Steering group Kick-off meeting, Jan 27, 2004