340 likes | 349 Views
Explore the commissioning of the cryogenic control system for the HIE-ISOLDE project at CERN, enhancing beam quality, intensity, and flexibility. Learn about the advanced equipment and project phases for this cutting-edge facility upgrade.
E N D
HIE ISOLDE commissioning of the cryogenic control system installation at CERN. LNL-INFN 22/07/2015 Dr. Marco Pezzetti (CERN) TE-CRG-CEControls and Electrical Support for cryogenics
The HIE-ISOLDE project ISOLDE Isotope Separator OnLine Device
The HIE-ISOLDE project • The High Intensity and Energy (HIE) ISOLDE project is a overall upgrade of the ISOLDE facility at CERN. • Consists in a superconducting linear accelerator of radioactive ion beams to study the nuclear physics. • Involves a increase of the intensity and energy in the beam and an improvement of its quality and flexibility.
The HIE-ISOLDE project • In order to achieve this energy, 32 superconducting RF cavities and 8 small solenoids, grouped in six cryo-modules (4.5 K), will be installed. • To comply with the project requirements it is necessary a new Cryo-station. Such is comprised of a compressor, coldbox and a distribution unit.
CP 199 198 CB DW JB5 JB3 JB2 JB4 JB6 JB1 RM Exp. Hall 170 CM1 CM2 CM6 CM5 CM4 CM3 CP + CB + Distribution unit
QSK1H-QYC32,33,34,42,43 = 199 QSC1H-EM03 = 198 QSR1H-QYC11 = 199 QSC1H-EM02 = 198 QSR1H-EM12 = 199 QSR1H-EM35 = 199 QSI1H-QYE21 = 199 QSK1H-QYC31 = 199 QSC1H-QYC01 = 198 199 198 Exp. Hall 170 List racks/cabinets
Compressor station 3.3 KV Motor High-stage Booster B. 198
Compressor Gas inlet Female rotor Oil Input Shaft Male rotor Gas outlet Slide valve Radial bearing Casing Hydraulic Cylinder
Compressor Stepper Buffer 1 & 2 Compressors 1 & 2 detail
Compressor Pressure preparation Regulation start request Step 20 Step 30 Step 40 Step 50 Step 60 CP normal run CP stopping CP START <20% <20%
Main characteristics of cryogenic equipment for HIE ISOLDE: • Equipment Unit Value • Cryoplant: (ex-LEP ALEPH plant) • Compressor suction (MPa) 0.104 • Compressor discharge (MPa) 1.4 • Nominal throughput (g s-1) 160 • Cooling power at 4.5 K 630 W & 1.5 g/s liquefaction • 2700 W at 52-75 K • Storage: (m3 STP) 2440 • Gas storage at 1.4 MPa (m3) 160 • Gas bags + buffer at 0.1 Mpa (m3) 200 • Helium Pumping Group: • Suction pressure (kPa) 1.54 • Discharge pressure (MPa) 0.102 • Nominal throughput (g/s) 2.0 B. 199
Diffusion pump Vacuum Primary pump • To pump out the high vacuum insulation spaces in the CB, transfer line and cryostat, two vacuum systems are needed. • In the case of the CB it generates high vacuum using a rotary pump (primary) & diffusion pump. • With this combination we get =~10 -6 mbar Vacuum System for CB
Cryomodules High β Low β • To meet the project needs, SixCryo-modules, split into two families, will be installed. 2 x 4 x High β Low β 5 RF Cavities & 1 Solenoid 6 RF Cavities & 2 Solenoid Total: 32 superconducting RF cavities & 8 solenoids
Cryomodules Project phase 3 B. 170
Cryomodules • Current status of the project: phase 1. Test in SM18-M9 In position, B.170 To be tested in the SM18-M9 over the next months. Currently in operation status at 4.5K.
Distribution & Cryomodule CP CB Transfer line + Jumper Box RM Vacuum Current leads Dewar Cryomodule
Jumper box Cryomodule FIP Profibus PA
Cryomodule Profibus PA FIP
Current leads Profibus DP Cabled signal
Return module Profibus PA
WorldFIP bus • 1 FEC CPU • 25 WorldFIP crates in the final phase. • 100 agents. • 56 channels installed for the infrastructure: • - 28 Connected. • - 28 Spare. • 768 channels expected for the 6 Cryomodules: • ~ 43% declared as spare. • ~ 69 connected for the CM in position 2.
Profibus • 1 CPU S7-300. • 1 Interface ET200. • 8 Link. • 16 Couplers PA: • 17 Slaves DP:
Operation Stepper – CM2 Operation Stepper
Conclusion • Cryogenic refurbishing done without main issues. • Cryogenic control system is a CERN cryogenic group standard. • Commissioning phase with cryomodulecooled down with LHe, progressing well. • LHelevel remains stable while tests on the solenoid and cavities are progressing. • Commissioning with beam expected next October 2015. • Second cryomoduleinstallation in progress, test in SM18 M9 end of the year.