1 / 27

Exploring Links between EIA, BREEAM and CEEQUAL

Exploring Links between EIA, BREEAM and CEEQUAL. SPEAKERS: Charlotte Brewin Associate RPS Ivan Rodrigeuz Technical Director URS. Angela Craddy Sustainability Consultant Mott MacDonald Helen Denham Environmental Coordinator Mott MacDonald. EIA, BREEAM and CEEQUAL

Download Presentation

Exploring Links between EIA, BREEAM and CEEQUAL

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Exploring Links between EIA, BREEAM and CEEQUAL SPEAKERS: Charlotte Brewin Associate RPS Ivan Rodrigeuz Technical Director URS Angela Craddy Sustainability Consultant Mott MacDonald Helen Denham Environmental Coordinator Mott MacDonald

  2. EIA, BREEAM and CEEQUAL How do they currently interact? Delivered by Charlotte Brewin, Associate at RPS 29th May 2014

  3. RIBA Plan of Work Timing of Assessments 0. Strategic Direction 4. Technical Design 1. Preparation & Brief 2. Concept Design 3. Developed Design 5. Construction 6. Handover & Close Out 7. In Use Planning Applications typically submitted at end of Stage 3 EIA BREEAM CEEQUAL

  4. Key Stages of EIA Planning Decision Screening Scoping Assessment of Effects Environmental Statement **New EIA Directive** Introducing potential new stage of Monitoring and Measurement

  5. 0 Strategic Key Stages of BREEAM and CEEQUAL Identify Project Strategy with appointed CEEQUAL Assessor Identify need for BREEAM rating CQ Pre-assessment scoping and scoring workshop Appoint BREEAM Assessor 2 Concept Design (Preliminary) 1 Preparation and Brief Register Scheme Register Scheme CQ evidence to assessor Predictive Assessment Provide CQ evidence to assessor 3 Developed Design (Outline) Provide CQ evidence to assessor Design Team Collates evidence; Assessor reviews and reports to BRE 4 Technical Design (Detailed) CQ Contractors Workshop and collate evidence 5 Construction BRE validates assessment and issues interim certificate 6 Handover & Close Out Construction team collates evidence and issues to BREEAM Assessor Project close out evidence collated and uploaded by assessor 7 Operation (Maintenance) Plan BREEAM Assessor submits final report to BRE for validation and final certification Final Evidence Verification/Ratification Board AWARD

  6. “An EIA is an assessment that feeds into the planning approvals process, but does not assess how well the subsequent project is actually delivered. Clearly because CEEQUAL Verification is completed at the end of the project it assesses what has actually happened. This also allows CEEQUAL to provide a means of assessing whether the recommendations from an EIA actually get implemented. CEEQUAL also provides a very good means for projects that do not require a formal EIA to comprehensively consider environmental issues.” Philip Charles, CEEQUAL

  7. Scope of Assessment

  8. Interaction in evidence base

  9. Information from EIA Authors:- Ecology Transport Landscape Noise Hydrology and Flood Risk BREEAM and Hinkley Point C Sustainability Strategy Construction Strategy Design Codes and Design Strategies BREEAM Predictive Assessments for 3 Main Buildings Design and Post Construction Assessments

  10. Angela Craddy Sustainability Consultant Water and Environment Helen Denham Environmental Manager Transportation And are they at risk of duplicating efforts?

  11. The opportunity or overlap? Increasing knowledge of detail Reducing flexibility to minimise impact Progress of the delivery process Sustainability opportunity Operation and maintenance Construction Commissioning and handover Optionselection Detaileddesign&procurement Decommissioning Project start-up Outlinedesign - Legislative minimum Environmental Impact Assessment - Best practice option for market leaders BREEAM and CEEQUAL Assessments

  12. Rating systems evolve and push “business as usual” to higher standards Each of the major rating systems is re-developed every 2 or 3 years to stay ahead of progressive building codes. Source: “USGBC White Paper – Greening the Codes”, US Green Building Council, 2010 12

  13. How does each method addresses… ecology? 6.1.1 Land of high ecological value 6.1.2 Consultation with Nature Conservation Organisations 6.1.3 Ecological Works Plan (Mandatory) 6.2.1 Surveys for protected species 6.2.2 Injurious or invasive species 6.3.1 Existing ecological features – Recommendations 6.3.2 Existing ecological features – monitoring 6.3.3 Existing ecological features – implementation success 6.4.1 New wildlife habitats 6.4.2 Special features for wildlife 6.4.3 Net increase in area / features of high value 6.5.1 Ongoing ecological management 6.5.2 Programme for monitoring EIA CEEQUAL LE 02 Ecological value of site and protection of ecological features LE 03 Mitigating ecological impact (Mandatory) LE 04 Enhancing site ecology LE 05 Long term impact on biodiversity • Screening • Scoping • Baseline surveys • Assessment of Impacts • Mitigation Conditioned at discretion of planning authority Manchester Civil Justice Centre – multi award winner BREEAM ‘Excellent’

  14. The opportunity? Motivations are different…. • legislation vs best practice • mitigate vs enhance • design vs whole-life-cycle

  15. SMART – EIA, CEEQUAL and BREEAM SMART – • Specific • Measurable • Achievable • Repeatable • Realistic • Timeframe NET2 Nottingham

  16. Delivery and Performance • EIA Statute driven • Mitigation of impacts by design • CQ and BREEAM seek • Intention • Commitment • Whole-life approach • Cradle to grave/gate • Targets and Quantifiable assessments • Mitigation measures • Operational Plans and Monitoring NET2 Nottingham

  17. Implementation Evidence Post EIA assessment - • Contract documents • Environmental Management Plans • Training and induction • Environmental Risk Register • Consents and permits • Generic and Specific Method Statements • Communication

  18. What EIA, BREEAM and CEEQUAL assessment methods can learn from each other? Ivan Rodriguez Technical Director 29 May 2014

  19. What can these assessment methods learn from each other? • Regulations & complexity • Reporting, Scoping & Measurement • Transparency • Impact on different project stages • Evidence gathering during design process • Quality assurance

  20. Regulations & complexity • EIAs can be complex, they follow a regulatory regime • Both BREEAM and CEEQUAL try to ensure that best practice (beyond regulations) is incorporated in the planning, design, construction and operation of Buildings and Infrastructure projects. BREEAM is required by some Local Planning Authorities whist CEEQUAL is voluntary. • BREEAM and CEEQUAL follow a Technical / Assessment manual based on specific criteria. • The BREEAM standard is subject to consultation and review every 3 years. This is aligned with the publication of Part L of Building Regulations.

  21. Reporting, scoping & measurement • The procedure for carrying out an EIA requires the developer to compile an Environmental Statement which describes the likely significant effects of the development on the environment and includes proposed mitigation measures. The approach for each EIA topic/issue can be quantitative or qualitative. • The CEEQUAL scoping process parallels the EIA scoping stage and this is useful in many ways. The assessment is carried out online and submitted to the verifier. • BREEAM is more rigid, allowances for scoping out credits are limited and higher flexibility is only allowed in Bespoke assessments. Both BREEAM and CEEQUAL ratings are evidence based and quantitative (%score , Ratings).

  22. Transparency • EIA is a very transparent assessment method, as the whole ES submitted to the LPA is publicly available • BREEAM and CEEQUAL are slightly less transparent to the general public (although this is changing with the publication of the case studies for both BREEAM Man 5 and CEEQUAL 2.5.2) these are not mandatory • The production and publication of detailed case studies for both BREEAM and CEEQUAL to enable lessons learnt and best practice to be disseminated should be mandatory

  23. Impact on different project stages • EIA, BREEAM and CEEQUAL should start at earliest project stage to maximise sustainability, added value and minimise risks. • The EIA approach is driven by regulation and it is specific for each development type, location, etc. • BREEAM can assess a Masterplan, the design and construction of a specific building ,and monitor its sustainability performance (yearly) through BREEAM In-use. • CEEQUAL starts with the strategy section and assess the design and construction of Infrastructure projects. Can also manage the maintenance of Term Contracts.

  24. Impact on different project stages Pre-application discussions EIA / Planning Step 1 Assessment and Interim Certification Step 2 Assessment Step 2 & 3 Ass & Certification Pre-assessment Design Stage Assessment Interim Design Certification Construction Ass & Certification Shell Certification Refub & FO Certification Assess & Certification Pre-assessment Design Stage (WTA Interim) Ass & Cert Construction Stage (WTA) Ass & Cert Maintenance term contract

  25. Evidence gathering during design process • EIA, CEEQUAL and BREEAM assessments cover similar topics/issues such as transport, ecology, noise, waste, ground contamination, flood risks etc. but they are treated in a different way. • EIA illustrates or predicts the effects of a development (or activity) that is likely to have a significant environmental effect, it then justifies how this effect can be mitigated against, through short, medium or long term measures. • CEEQUAL and BREEAM usually set targets at the beginning of the design process, in terms of a score that should be achieved.

  26. Quality assurance • An EIA can be challenged as the ES is publicly available so thorough internal and legal review is key. • CEEQUAL assessment have a two tier Quality Assurance process (verification and ratification). This QA level should be maintained. • BREEAM assessments are quality assured by BRE Global Limited, which is an independent certification body accredited by the United Kingdom Accreditation Service (UKAS) and certified to ISO 9001 for all its BREEAM related activities.

  27. SUMMARY - Links between EIA, BREEAM and CEEQUAL • Any comments or questions? Collaborative Approach Market Driven Commercial Competitive Quality Markers Self – Regulation Best practice Statutory Compliance Whole Lifecycle approach Independent Certification and Ratification Quality, sustainable and environmental developments

More Related