1 / 15

Vacuum System Failures at HERA

Vacuum System Failures at HERA. M.Seidel, DESY OLAV Workshop, CERN, April 12, 2005. Categorization of Failures. Non-Interrupting Failures getter pump power supply failure cable failure; radiation damage pump address or location error (software)

larrywood
Download Presentation

Vacuum System Failures at HERA

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Vacuum System Failures at HERA M.Seidel, DESY OLAV Workshop, CERN, April 12, 2005

  2. Categorization of Failures Non-Interrupting Failures • getter pump power supply failure • cable failure; radiation damage • pump address or location error (software) • NEG pump heating circuit – shortcut to ground! • vacuum interlock electronics failure (dangerous!) • collimator damage by beam (hard to diagnose)

  3. Categorization (2) Interrupting Failures (Leaks!) • beam induced leaks by heating/thermal shock • leaks by electrical failure in feedthroughts • water-vacuum leaks at brazing joint • RF window breaks by heat load (after long term metallization) • fatigue failure at bellows (wire scanner, collimator) (not discussed here → systematic problems)

  4. Example non-interrupting failure – Proton Collimator Damage Tungsten Collimator Jaw, 40cm long melting point: 3422 °C ! p-beam: 920GeV, 100mA damage was not realized during operation; mechanism not clear Result: reduced collimation efficiency; hard to diagnose!

  5. Interrupting Failure: p-Loss induced leak in VAT sealed flange connection • specially shaped vacuum chamber; VAT sealed; located in half quad in IR • after uncontrolled beam loss (dump fired too late): • high activation 2mSv/hour • leak at seal >10-6 mbar l/sec

  6. Model for p-Loss induced leak Newton’s law: τ loss time approx. 2ms! yield strength of seal exceeded by compression force for beam energy deposition >4% @65mA stored  very well possible!

  7. Leaks from asymmetric heating of Conflat flange connections • leak occurs when heat load at flange is switched off suddenly • laboratory tests show this can happen for ΔT=40°C !! • hard SR penetrates chamber or absorber and heats flange from outside typical signature lab-experiments asymetric heating

  8. Collapse of steel chamber from SR heating in 2004 keyhole chamber that collapsed, right side of IR schematic layout HERA IR upstream absorber - gap in side-channel opened up for background reasons

  9. collapsed chamber • chamber collapsed from heating by mis-steered SR fan • Temperature more than 1000°C • orbit feedback failed inside view

  10. New interlock – flat T-sensors • between chamber and magnet poles: PT 100 film sensors; thickness 0.4mm • 5 sensors each side; • distance 30cm • already 3 beam dumps by this interlock in 2005/04

  11. High Current Electrical Feed-Throughs • Problem: NEG heating circuits or Ti sublimation pump filaments are operated at relatively high currents – 30-50Amps • high electrical power can be dissipated at shortcuts or transitional resistance (connectors)

  12. NEG Pump Feed-Through • internal shortcut produced an arc resulting in a macroscopic leak • happened during activation!!!

  13. Water-Vacuum Leak in Brazing Connection • tuning cylinder RF cavity; internally water cooled tuner and cavity

  14. Another Tuning Cylinder... same type of device: massive cracks developed theory: bubble of air reduced cooling at top of cylinder

  15. Summary • most serious trouble happened with heating by particle beam or SR → build your system passively safe if possible; any orbit that circulates will occur! • high current electrical feed-throughs are problematic; especially with a large number of components • power supplies and electronics fail most often; however, this does not interrupt operation (mostly)

More Related