110 likes | 253 Views
Hall A Infrastructure and the M oller P arity Ex periment “AMPEX”. Paul Brindza August 14, 2008. Hall A Major Equipment. Two SC high resolution (<10^-4) Spectrometers HRS left 4.0 GeV /c HRS right 2.8 GeV /c 12.5 degrees minimum lab angle stand alone
E N D
Hall A Infrastructure and the MollerParity Experiment“AMPEX” Paul Brindza August 14, 2008
Hall A Major Equipment • Two SC high resolution (<10^-4) Spectrometers HRS left 4.0 GeV/c HRS right 2.8 GeV/c 12.5 degrees minimum lab angle stand alone 6.0 degrees with SC septa to 4.0 GeV/c 5.0 degrees with RT septa to ~ 2.4 GeV/c • Big Bite spectrometer and detectors • Calorimeters and neutron detectors
Hall A Target Systems • Cryo-target (3 cell/ ~800 watts) (H, D, He) • Polarized HE3 target system • Waterfall Target • UVA polarized target near future
Hall A Beam Line Instrumentation • Compton Polarimeter upgrade to 11 GeV/c capable of CW non invasive measurement • Moller Polarimeter upgrade to SC magnet • Arc Energy Measurement system upgrade to 11 GeV • Beam Girder just upstream of pivot has super harps , BPM’s & BCM’s.
Hall A Installed Utilities • Installed Hall A AC power 480 V 1800 A compare to Hall C 1800 A plus 2400 A @ 480 V. • Spare penetrations available for more AC in “A” • Installed LCW- same capacity as “C” at the wall, internal piping is smaller, easy to fix. • Installed Cryo ~ 500 watts at 4.4 K for HRS’ • LHe at 4.4 K near pivot (xtra SC magnet coolant) • GHe at 15 K at pivot (~ 1KW cryo-target coolant)
Hall A DC Power Supplies • 8 SC magnet power supplies 5-10 Volts, 2000-3500 Amps • Big Bite DC supply 125 Volts 750 Amps • New “spare” DC supply 10V 3000 Amps • Lots of room for more (loaners) HES and HKS dipole DC supplies SOS DC supplies (3) Qweak DC supply
Cryogenic Capacity-ESR Upgrade • Present ESR is ~ 1400 watts stand alone at 4K and ~1000 watts at 15 K • Present program requires constant supplement from CHL of ~ 10 gm/sec • ESR upgrade is part of 6 GeV hardening preparation work for the 12 GeV era • ESR upgrade to 4 Kilo watt capacity • ESR upgrade plan - operational ~ 2014
Torus Version of Moller Experiment From Dave MackAt least two more configurations are under consideration World’s highest power LH2 target Scattered electrons drifted to Q2-defining collimator Moeller-focusing, resistive spectrometer Fits in endstation A or C
e2ePV Target RequirementsFrom Dave Mack • Target cooling power requirements are about 2.4 times more aggressive than Qw(p) ( 5 kiloWatt target) • Qw(p) already plans to increase helicity reversal to nearly 300Hz in order to “freeze” density fluctuations. • Qw(p) target groups are now using finite element analysis codes to upgrade existing G0 design. • Astonishingly, sufficient cooling power is available on site, though more refrigeration would allow more flexibility in scheduling. Highest priority is to build and test the Qw(p) target.
Moller Parity Torus Geometry in Hall ACryo-Target at -1.5 meter from pivot
Conclusion-Moller Parity in Hall A • Torus Version of Moller Experiment fits in Hall A Locate Cryo-target at -1.5 M from pivot Overall experiment length limited to ~ 27 M. • Other Moller Experiment schemes are possible but may require displacement of some Hall A Infrastructure • 5 KW Cryo-target power is available now but only with significant Lab wide scheduling concessions without the planned ESR upgrade in 2014. • AC, LCW, DC capacity adequate now for a SC magnet Moller Parity Experiment. • LCW, AC & DC capacity for a resistive magnet Moller Parity Experiment may require an upgrade. • AMPEX is a catchy name!