1 / 12

Septum 16 shielding increase

Septum 16 shielding increase. 19 November 2013 . Requested : - Additionnal depth of earth of between 1.2m and 3.4m over Septum 16 area Constraints : Existing structures not strong enough to take the additional load

latona
Download Presentation

Septum 16 shielding increase

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Septum 16 shieldingincrease 19 November 2013

  2. Requested: • - Additionnaldepth of earth of between 1.2m and 3.4m over Septum 16 area • Constraints: • Existing structures not strong enough to take the additional load • Area with a very complex geometry (PS, Linac 2&3, Leir, TT2, . .) • Works must have no influence or impact on the existing structures

  3. -A new load-bearing structure taking the weight of the additionalearth and redirectingitinto the bedrockunderneath. -The structure consists of a 1.10 m thick reinforced concrete slab and the additional depth of backfill will be placed directly on the slab. -The slab rests on drilled piles and on intermittent supports on the tunnel roof Proposed solution :

  4. Slabdeformation: 56 mm 51 mm

  5. To protect the existing structures, the transfer slab must guarantee that even after long-term deformation the load-bearing relief structure does not under any circumstances come to rest on the existing structures. • To this end, it was foreseen to use a biodegradable honeycomb cardboard formwork that could be bedissolved with water. This procedure guaranteed that, once water had been injected to dissolve the cardboard, a void of 10 cm remained after concreting, which was more than enough to allow for the long-term deformation of the slab

  6. Status– 19 November 2013 • Adjudication of the works on 19 June 2013 • June-July 2013 - Preparatoryworks • July 2013 – Earthworks • September2013 - Pilingworks • 2 October 2013 – Start of concretingworks – Stage 1a • 8 October 2013 – Works stoppage – The biodegradableformworkgetswetbeforeconcreting ! • 8-16 October 2013 – Removal of the formwork&reinforcement of stages 1b and 2a • 18 October 2013 - a new method is developed and tested: sand instead of biodegradable formwork, to be pumped out prior to backfilling • Now – Stages 1b and 2a concreted using the new method

  7. Somepictures of the works: Pilingworks – September 2013 Earthworks - July 2013

  8. Concretingworkswithbiocofra – October 2013

  9. Demolitionworks – 8-16 October 2013

  10. New concretingoperationswithsand – November 2013

  11. New schedule End of the works: 15/03/2013 (to beconfirmeddepending on the speed in pumping the sand)

  12. Thank you for your attention

More Related