Mid-Bay Bridge Connector Phase II and III. December 2011 Project Update. Milestone Highlights - Start Date: February 14, 2011 - November Completion Date: January 28, 2014 December Completion Date: January 28, 2014 December CPM Schedule: Approved Time Highlights
E N D
Mid-Bay Bridge Connector Phase II and III December 2011 Project Update
Milestone Highlights • - Start Date: February 14, 2011 • - November Completion Date: January 28, 2014 • December Completion Date: January 28, 2014 • December CPM Schedule: Approved Time Highlights • Original Contract Day: 298 of 1080 • Weather Days: 3 • Change Order Days: 0 • Total Contract Days: 298 of 1083 Contract Amount Highlights • Contract Amount: $ 48,732465.03 • Change Order Amount: $ 25,000.00 • Fuel and Bits Adjustment: $ 343,237.83 • New Contract Amount: $49,100,702.86 • Amount Paid To Date: $ 14,969,680.06
Turkey Creek Bridge Rocky Creek Bridge Range Road Bridge Phase II Completion Dates
Range Road Bridge Range Road Bridge – Milestones
Rocky Creek Bridge Rocky Creek Bridge – Milestones
Turkey Creek Bridge Turkey Creek Bridge – Milestones
Fox Head Branch Bridge Mill Creek Bridge SR85 Bridge Swift Creek Bridge SR285 Bridge Range Road Bridge Phase III Completion Dates
SR285 Bridge Range Road Bridge SR 285 Bridge – Milestones
Swift Creek Bridge Range Road Bridge Swift Creek Bridge – Milestones
Fox Head Branch Bridge Range Road Bridge Fox Head Branch Bridge – Milestones
Mill Creek Bridge Range Road Bridge Mill Creek Bridge – Milestones
SR85 Bridge Range Road Bridge SR 85 Bridge – Milestones