Scheduling Concrete DispatchCC-005 James Wagner jwagner@commandalkon.com Cell 612-991-5912
Scheduling Concrete Dispatch Present how dispatch managers can accurately plan, schedule, and track your dispatch day to achieve optimal service and efficiency levels. Scheduling Concrete Dispatch
Topics • Introduction • Scheduling nomenclature and setup • Using Scheduling properly • Scheduling special situations • Troubleshooting • Map Pages Scheduling Concrete Dispatch
Concrete Axioms • In a buyers market efficiency is difficult, service is easy • The opposite is true in a sellers market • Reducing delivery costs requires scheduling • Improving service requires scheduling • You cannot dispatch your way to success • You can’t schedule orders you don’t have • You can’t schedule unreliableWill Calls • You can’t schedule orders that aren’t accurate • Once called out, drivers are a fixed cost • You cannot improve unless you change. • You can’t improve if customers run your business • Anybody can be on time 1st round Scheduling Concrete Dispatch
Scheduling should; • Display truck commitments • Show when new orders can be accepted • Show if overbooked or underbooked • Help determine how many trucks to use • Produce a driver report time schedule • Indicate when to begin thinking of wash up • Determine if the plant(s) can load the orders • Display loading conflicts (preloading) • Indicate when one will be “out of the woods” • List need for raw materials by time of day Scheduling Concrete Dispatch
Scheduling requires no effort except honesty No additional data is needed Orders are needed for shipping and billing Ticketing initiates rescheduling of the order Orders need mix and product info which is used for materials forecasting Scheduling Concrete Dispatch
Scheduling lets everyone know the plan Entering orders as they are taken ensures that the schedule is up-to-date Commitments can be make without seeking permission Promotes teamwork Computer scheduling is fast, not smart Much faster than a human Able to recalculate and display changes immediately Scheduling Concrete Dispatch
Scenarios - worse case 17:00 - no business for tomorrow Scheduling Concrete Dispatch
Scenarios - nearly worse case17:00 - little business for tomorrow Scheduling Concrete Dispatch
Scenarios - Bad situation 17:00 - too many W/C for tomorrow Scheduling Concrete Dispatch
Scenarios – Tolerable17:00 - first round known Scheduling Concrete Dispatch
Scenarios – Workable17:00 - First round known, bal = W/C Scheduling Concrete Dispatch
runs quite flat ramps up ramps down Plant 1 Minimally exceeds the trucks available Scenarios – “Ideal17:00 - All orders known Scheduling Concrete Dispatch
Scenarios – Bad 17:00 – Excessively Overbooked Scheduling Concrete Dispatch
Scenarios – Bad 17:00 – Excessively Overbooked • Many orders delivered late • Work not handled overflows to later times • New list of customers to NOT hurt tomorrow. Scheduling Concrete Dispatch
Scenarios - Bad17:00 - Large gap in day’s business Trucks wait in yard for PM business. Scheduling Concrete Dispatch
What displays are needed For single plant operations • Truck demand • Plant loading • Fleet adjust (when out of woods) • Preload (loading conflicts) Scheduling Concrete Dispatch
What displays are needed For two plant operations • Truck demand for each plant individually with both plants in background. • Plant loading – each plant • Fleet adjust (when out of woods) each plant • Preload (loading conflicts) each plant Scheduling Concrete Dispatch
What displays are needed For multiple plant operations • Truck demand for each plant individually with common market plants in background. • Truck demand for combination of plants that can share trucks or market i.e. 1,2 & 3 plus 2,3 & 4 plus 1, 3 & 4 • Plant loading – each plant • Fleet adjust (when out of woods) each plant • Preload (loading conflicts) each plant Scheduling Concrete Dispatch
Scheduling Configuration options • Multiple scheduling displays • Combined tracking and scheduling • Foreground/ background • Report lines • Display lines • Trucks, quantity, loads • Truck types • Loads per plant Scheduling Concrete Dispatch
Use menu Scheduling Concrete Dispatch
Double click on screen Scheduling Concrete Dispatch
Setup options Scheduling Concrete Dispatch
Set up of Plants Scheduling Concrete Dispatch
Foreground/ Background Advantages; • Try to even out the demand at individual plants • See which plant has available trucks • Determine where and when to redeploy trucks Scheduling Concrete Dispatch
Plant 1 = 8? Plant 2 = 9? How many trucks would you use? 8 + 9 = 17 Scheduling Concrete Dispatch
How many trucks would you use? Together = 15 Why? Scheduling Concrete Dispatch
How many trucks would you use? The peak at plant 2 occurs earlier than the peak at plant 1. Scheduling Concrete Dispatch
Foreground/ background display Scheduling Concrete Dispatch
When foreground /background? • When plants are in the same market area • When plants can share trucks • When plants can help service orders • When trucks can maintain radio contact with all plants in that area. • It is ok to display a plant in more than one display. • 1,2 & 3 together • 3,4 & 5 together • 4,5 & 6 together Scheduling Concrete Dispatch
When not foreground /background? • When plants are in different market area • When market areas are different • Residential versus commercial • When plants cannot share trucks • When plants cannot help service orders Scheduling Concrete Dispatch
Multiple displays – reasons Special displays Purpose; • To display 1,2,4 or 6 situations on one screen. • Multiple plants • Combinations of plants • Truck types • Loading schedules Scheduling Concrete Dispatch
Multiple displays – 1 plant Scheduling Concrete Dispatch
Multiple displays - 2 plants Scheduling Concrete Dispatch
Multiple displays – 4 plants 2 truck types Scheduling Concrete Dispatch
Multiple displays – specific trucks Special truck types scheduling Purpose; • To display the demand for a specific but limited type of truck. Scheduling Concrete Dispatch
Set up of Truck types Ensure <None> is ticked on Includes trucks for orders with no specified truck type Scheduling Concrete Dispatch
Set up of Truck types This order has no Truck Type specified yet we still want to see the truck demand in scheduling Scheduling Concrete Dispatch
Schedule - Truck types Scheduling Concrete Dispatch
Setting up scheduling parameters • Plant file • Truck file Scheduling Concrete Dispatch
Pre-load is queuing up Lead time is used for driver call in Post-load is slumping Wash is the default if none specified Loading is most important 5 minutes = 12 loads/ hour Plant Scheduling Parameters Scheduling Concrete Dispatch
Plant Scheduling Parameters Sets the default green truck line position on Dynamic Scheduling Sets max line in Quantity/hr schedule Sets normal or average line in Quantity/hr schedule Scheduling Concrete Dispatch
Truck Scheduling Parameters The truck’s Scheduled Load Size is the default for scheduling. The Minimum and Maximum only produce warnings at ticketing. The truck’s scheduling data is contained in the scheduling tab Scheduling Concrete Dispatch
Dynamic Plant Fleet Size This feature adjusts the green fleet line at a plant when a truck ALREADY in service is sent to another plant. It does NOT alter the fleet line at In-Service or Out-Of-Service statuses. Scheduling Concrete Dispatch
Using Scheduling Scheduling Concrete Dispatch
Entering order data accurately • Priority customers • Ordered versus scheduled quantity • Correct Rate • Accurate Travel • Order backs • Hold quantity • Load size Scheduling Concrete Dispatch