An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. GLAST LAT Tracker Tower7/9 Pre-Ship Review Luca.latronico@pi.infn.it INFN-Pisa

  2. Tower 7 - Assembly and test highlights tray17 replacement • June 14 - July 4, 2005 (INFN-Pisa) : • assembly of complete tray stack • incomplete cable set (C0,C1,C2,C3,C4,C7) • Sidewalls, alignment • July 7-15, 2005 (Alenia-Roma) : • VIB, TVAC test RUN I • NCR 544 layerX17 noise anomaly • July 25-26, 2005 (INFN-Pisa) : • Tray 17 replacement • C5 installation • July 28 – August 31, 2005 (Alenia-Roma) • TVAC (7/28-8/4) RUN II • VIB (8/31) RUN II (Z axis only) • September 1-5, 2005 (INFN-Pisa) : • C6 installation • Solithane, EMI taping • Alignment verification, final CPT • Full EIDP details (soon) at: • http://glast.pi.infn.it tray to be replaced Aluminum service sidewall

  3. Tower 7 – Environmental test runs configurations

  4. Tower 7 Delivery configuration Tower PN: LAT-DS-00722 (rev3) Tower SN: 7 Details on NCR 530

  5. Tower 7 – Configuration and mechanical verifications Configuration: • Kapton tape and foam applied on the flex cables as per LAT-DS-00722 • 4 layers of Poron foam 0.037 THK used on Bottom and Top Tray (–X) side (in place of 5 layers) • Base Plate assembly: • Torque of nuts 5.3 Nm, spec is (5.08 +0.56/-0 Nm) Alignment, Mass, COG: • Tower 7 well aligned and inside stayclear • Mass (32.705Kg) and CG near estimated values (when used real masses) • Full data available from EIDP and INFN-PISA web site

  6. Tower 7 – Open NCRs • INFN/PI-530: environmental test in non-flight configuration • both environmental test runs were performed with missing cables, as agreed by an MRB • As a consequence of the missing solithane, 4 screws loss nominal torque and 1 was halfway unscrewed on one sidewall after Z-axis vibrations: the screws were re-torqued to spec and the following X and Y axis vibrations did not show any torque loss • the NCR can be closed • INFN/PI-543: layer X7 not read out (TVAC RUN I) • X7 could not be readout at power up after vib test. X7 was properly read at the following and first switch on during TVAC • The problem is due to a known and documented issue with resetting MCM (NCR 417) with missing cables • To avoid the many and unknown number of power cycle needed to re-establish a good configuration with as many readable layers as possible, hot/cold switch on and off were not performed • the NCR can be closed • INFN/PI-544: layer X17 noisy at hot soak (TVAC RUN I) • As per MRB decision, tray 17 (MID010) was replaced with a new tray, and tower7 retested • the NCR can be closed • INFN/PI-570: cold/hot power off/on not performed (TVAC RUN II) • Same as NCR 543 • the NCR can be closed • INFN/PI-547: Vacuum level out of specification (TVAC RUN I) • The situation is similar to earlier TVAC tests and the proposal is to accept the test as for previous MRBs. Tower 6 was tested with tower 7 RUN I and the same NCR was closed

  7. Tower 7 – Bad channels NCR 534: 2 layers (Y2, X5) sometimes out of spec due to fluctuations in noisy channels; the NCR can be closed X17 fixed after tray M010 replacement X5 showed 1 noisy ladder when ramping from 3rd cold to 4th hot soak: similar isolated anomalies, appearing randomly and only once were observed in other towers and are very likely caused by noise pickup dependent on the setup and/or the readout system (remember NCR 461 on the interference between the 2 towers DAQ causing test failures)

  8. Tower 7 - Efficiency taken in Alenia after 2nd TVAC All layers well within spec (eff > 98%) Differences correlated to bad channels No change after z-axis vib retest

  9. Tower 7 TVAC – vacuum out of spec RUN I Same behaviour as previous tests – proposal is to accept the test: • Vacuum slightly higher than spec (~> 10-4 vs 5x10-5 Torr) during hot soaks • Vacuum level improving with time • same pressure behaviour in dry run with MGSE Same behaviour as tower6 TVAC, accepted during preship review (corresponding NCR 546 was closed)

  10. Tower 9 - Assembly and test highlights • July 8-15, 2005 (INFN-Pisa) : • assembly of complete tray stack • incomplete cable set (C0-non-flight,C3 missing,C7-non-flight) • Sidewalls, alignment • July 25 – august 4, 2005 (Alenia-Roma) : • VIB, TVAC • September 5-7, 2005 (INFN-Pisa) : • C0, C7 replacement with flight cables • C3 installation • Solithane, EMI taping • Alignment verification, final CPT • Full EIDP details (soon) at: • http://glast.pi.infn.it tray to be replaced

  11. Tower 9 – Configuration and mechanical verifications Configuration: • Kapton tape and foam applied on the flex cables as per LAT-DS-00722 • 4 layers of Poron foam 0.037 THK used on Bottom and Top Tray (–X) side (in place of 5 layers) • Base Plate assembly: • Torque of nuts 5.4 Nm, spec is (5.08 +0.56/-0 Nm) Alignment, Mass, COG: • Tower 9 well aligned and inside stayclear • Mass (32.840Kg) and CG near estimated values (when used real masses) • Full data available from EIDP and INFN-PISA web site

  12. Tower 9 – Open NCRs • INFN/PI-541: environmental test in non-flight configuration • environmental test were performed with missing cables, as agreed by an MRB • Missing cables are the consequence of the following NCRs • the NCR can be closed • INFN/PI-560: cold/hot power off/on not performed • To avoid the many and unknown number of power cycle needed to re-establish a good configuration with as many readable layers as possible, hot/cold switch on and off were not performed after a satisfactory running condition was found • the NCR can be closed • INFN/PI-559: layers X2 and X12 not read out • Despite the many power cycles it was never possible to reset the tower as to read these layers; when a practical configuration was found with all layers readable but these 2, TVAC was run with such two layers disabled • Post environmental test show no problem in the performance of these two layers (see next slide) • the NCR can be closed

  13. Tower 9 - Efficiency All layers well within spec (eff > 98%) X2 @99.8%, X12@99.9% Total bad channels in tower ~50