An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FIREWATER PUMP P6001A installation FEB 2006 as reported by Mark Dye

  2. N East isolation gate West isolation gate P6003B P6003A P6001A P6001B P6002A P6002B East firewater pond West firewater pond Pump house layout

  3. Unpacking P6001A

  4. This is the pumps hydraulic end With the pump submerged, the water flows up through the shaft housing

  5. The business end!

  6. The pump and first pipe spool being lowered into the well…

  7. …into the icy water below

  8. Looking down through the spool to the pump top below

  9. A shaft bearing is installed between each pipe spool and clamped between the flanges The bearing is water lubricated and made of PTFE

  10. The shaft joining piece has a left hand thread! The next pipe spool is lowered into position

  11. Jointing compound

  12. The flanges are bolted together, The support is opened, and the pump is lowered. then torqued down to 175 ft-lbs.

  13. With all the parts assembled we have… The pump at approx 2.5 metres Three spools at 1.7 metres each One spool at 1 metre Giving a total of 8.6 metres Now we need the stuffing box assembly

  14. The stuffing box assembly is unpacked, And the top bearing assembly removed.

  15. The top bearing assembly is keyed to the shaft because it also contains a ratchet device to prevent back turning of the shaft.

  16. STEADY AS SHE GOES!!!

  17. Thread the shaft through and line up the spool bolts. The whole assembly now needs to be lifted to remove the spool support. The combined weight is now 3.7 tonnes.

  18. The top bearing is re-installed and keyed to the shaft.

  19. The coupling housing and motor stand installed. The coolingwater supply, …and return, and constant level oiler is fitted.

  20. 10kv Electric motor installed

  21. PUMP SPECIFICATIONS Pump speed 1480rpm Test pressure 33barg Rated flow 240 l/s (864t/hr) Head 158.4 mtrs. (15 barg)

  22. The jockey pump is exactly the same as the main pumps, …only in miniature!

  23. The pump had it’s first test run… …flushing firemains into the night!