1 / 9

Status Update: Reliability & Market Power Mitigation Assessment Stakeholder Meeting

This is a status update for the Reliability & Market Power Mitigation Study, including data collection progress, key inputs, study process, and timeline.

leewalter
Download Presentation

Status Update: Reliability & Market Power Mitigation Assessment Stakeholder Meeting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Status Update for Reliability/Market Power Mitigation Assessment Stakeholder Meeting April 16, 2008 Austin, TX

  2. Reliability & Market Power Mitigation Study Model : Status Update • Data collection effort in process • SPP has received most of the input from ETI with two conference calls to discuss the data • Last set of data was recently received by ETI (SPP is still reviewing it) • Study case will be ready by April end (Reliability Study) and by May end (MP Mitigation Study) for stakeholder review

  3. Reliability Study Model : Key Inputs • Generation Inputs • Two new generating plant to serve ETEC load (150 MW each) at Cypress and Jacinto • Cottonwood plant will be considered in Eastern Interconnect • Sensitivity to be run with Cottonwood connecting into ERCOT • Transmission Inputs • ETI’s 2008-2010 construction plan • STEP plan (2008-2017) approved by SPP BOD • Transactions (Interchange) • Latest transactions (interchange) for 2012 based on ETI and SPP’s OASIS • Only Long-term Firm transactions will be considered

  4. Reliability Study Process : Key Inputs • SPP-ETI Transfer Scenario • Units in SPP footprint are ramped up based on reserve capacity • Units in ETI will be backed down based on heat rate characteristics • RMR units in ETI will be backed down when other units reach their minimum limit • Units not owned/operated by ETI will not backed down • Contingencies Examined • Breaker to Breaker in ETI • 100 kV and higher outside ETI • 100 kV and higher in SPP • Monitored Transmission Facilities • 100 kV and above in SPP, ETI and Rest of Entergy • Interfaces, identified flowgates

  5. Market Power Mitigation Study : Key Inputs • The latest version of PROMOD IV with 6 digit bus numbers will be used • Generation Details • ETI : Publicly available data based on typical characteristics • SPP: Actual Data as provided by SPP members • RMR details will be modeled using Proxy approach (key interfaces, flowgates) • Typical Load shape will be used for ETI for hourly load forecast in study year (2012) • Fuel price data and other inputs will be coordinated with ERCOT for consistency

  6. Time Line • Final input data will be ready by April end • Study Models Finalized • Reliability Assessment Study Model : April 2008 • MP Mitigation Assessment Study Model : May 2008 • Preliminary Results Expected • Reliability Assessment : July 2008 • MP Mitigation Assessment : September 2008

  7. Questions?

  8. Mak NagleManager, Technical Studies and Modeling501-614-3564mnagle@spp.org

More Related