Approval of STP, TAP & Resurfacing PROJECTS. Resolutions 2014-01, 2014-02 and 2014-03 AMATS Committee Meetings January 2014. 2014 Project Funding. STP, TAP and Resurfacing Programs 133 applications submitted for funding Requests for over $114 million Over-program
E N D
Approval of STP, TAP & Resurfacing PROJECTS Resolutions 2014-01, 2014-02 and 2014-03 AMATS Committee Meetings January 2014
2014 Project Funding • STP, TAP and Resurfacing Programs • 133 applications submitted for funding • Requests for over $114 million • Over-program • Reduce carryover balances • Projects programmed to FY 2021
Recommended Funding by Program STP - $17.9 million TAP - $3.9 million Resurfacing - $6.8 million Total of $28.7 million
Next Steps • Notice of approval of funds • 45 days to submit programming package to ODOT • Scope meetings • Future Rounds of Funding • CMAQ (statewide program) - spring of 2014 • STP,TAP and Resurfacing – fall of 2015
Committee Approval • Resolution 2014 – 01 Surface Transportation Program projects • Resolution 2014 – 02 Transportation Alternatives Program projects • Resolution 2014 – 03 Resurfacing Program projects